M/S. Motilal Agarwala v. State of West Bengal & Anr.

Civil Appeal · 2025 INSC 1062Decided 28 Aug 2025
Civil Appeal No. 4480 of 2016
Justice J.B. Pardiwala · Justice K.V. Viswanathan

Background

An arbitrator passed an award in favour of the appellant contractor against the State of West Bengal on 12.11.2013. A signed photocopy of the award was collected the same day by a junior official (an Assistant Engineer) who was present at the proceedings but never informed his department. The State only learned of the award when the appellant began execution proceedings, and it filed its challenge under Section 34 of the Arbitration and Conciliation Act, 1996 on 20.03.2014. The trial court held this challenge was time-barred (the 90-day limit having run from 12.11.2013), but the Calcutta High Court reversed, holding limitation only starts once the award is properly served on an actual "party" to the arbitration.

Decision Breakdown

The Supreme Court agreed with the High Court and dismissed the contractor's appeal. It held that under Section 31(5) and Section 2(1)(h) of the Arbitration Act, a "party" means the actual party to the arbitration agreement, here the State department represented through its Secretary or Executive Engineer, not any employee or representative who merely attended proceedings or collected a copy. Relying on its earlier rulings in Tecco Trichy Engineers and Benarsi Krishna Committee, the Court held that in large organisations like government departments, the limitation clock starts only when the award reaches the person who actually has authority and knowledge to decide whether to challenge it, not a subordinate who received a photocopy informally. Since the award was never validly delivered to a competent decision-maker before the State's application, the Section 34 challenge was not time-barred.

Lesson Learnt

In arbitration involving government bodies or large organisations, the limitation period to challenge an award runs from proper delivery of a signed copy to the actual decision-making authority (not any employee who happens to receive it): a lesson relevant to anyone dealing with institutional counterparties in arbitration.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case