M/s. Narinder Singh and Sons v. Union of India

Civil Appeal · 2021 INSC 747Decided 18 Nov 2021
Civil Appeal No. 6734 of 2021
Justice M.R. Shah · Justice Sanjiv Khanna

Background

The appellant contractor was awarded a Railway tender in 1993 for washing-line work at Jammu Tawi station; the Railways terminated the contract in 1996 alleging non-performance, while the contractor alleged the Railways had repeatedly changed the scope of work. After years of litigation over appointing an arbitrator, a retired judge was appointed and passed an ex parte award of over Rs.20 lakh in the contractor's favour in 2010. The Railways' objections to that award were dismissed by the trial court but upheld by the Punjab and Haryana High Court, which set aside the award for violating natural justice and excessive haste, prompting the contractor's appeal to the Supreme Court.

Decision Breakdown

The Supreme Court agreed with the High Court that the award deserved to be set aside, finding that the arbitrator had rushed proceedings, refusing to properly consider the Railways' evidence affidavit and denying it a fair opportunity to cross-examine a key witness, which amounted to the Railways being "unable to present its case" and the award being in conflict with public policy under Section 34 of the Arbitration Act. With both parties' agreement during the hearing, the Court appointed a new arbitrator (a retired High Court judge) to decide the dispute afresh, directed that arbitration resume from the stage where cross-examination had been wrongly denied, fixed how the arbitration costs would be shared, and left the question of interest open for the new arbitrator to decide. The civil appeal itself was thereby finally disposed of.

Lesson Learnt

An arbitrator who denies a party a fair chance to present evidence or cross-examine witnesses, even in the name of speedy disposal, risks having the award struck down for violating natural justice; speed in arbitration cannot come at the cost of a fair hearing for both sides.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case