M/s. Parsvnath Film City Ltd. v. Chandigarh Administration

Civil Appeal · 2025 INSC 464Decided 20 Mar 2025
C.A. No.-006162-006162 - 2016
Mrs. Justice B.V. Nagarathna · Justice Satish Chandra Sharma

Background

Chandigarh Administration selected Parsvnath Film City Ltd. as the developer for a large Multimedia-cum-Film City project after competitive bidding, and the parties signed a Development Agreement in March 2007 under which the company paid Rs. 47.75 crore (25% of the bid price) upfront. The project stalled because the Administration took 16.5 months to hand over a demarcation plan for the site and never removed high-tension power lines running through it, making it impossible for the company to begin construction; when talks to resolve the impasse went nowhere, the company declared the agreement frustrated, and the Administration then terminated the contract, blaming the company and forfeiting the entire upfront payment.

Decision Breakdown

The Supreme Court restored (with modifications) the Arbitral Tribunal's award, which had already found the delay was caused by the Chandigarh Administration, not the developer, and had ordered the money refunded. The Punjab and Haryana High Court had wrongly set aside that award, incorrectly treating the developer as having unjustifiably abandoned the project. The Supreme Court held that under the Agreement's own terms, delay caused by the government side had to be excluded from the project timeline, that the government could not fault the developer for problems (encumbered land, undelivered demarcation plan) it had itself created and later admitted to in meetings, and that a court's power to interfere with an arbitral award is narrow. It cannot re-appreciate evidence or substitute its own view unless the award is genuinely against public policy or law. The Court upheld the refund of the Rs. 47.75 crore deposit and actual expenses, but reduced the interest rate from 12% to 8% per annum (rising back to 12% if payment wasn't made by a set deadline) and disallowed a separate compensation-for-loss amount as duplicative of the interest already awarded.

Lesson Learnt

When a government or public authority fails to deliver on its own contractual obligations (like handing over usable, encumbrance-free land on time) it cannot then blame the private party and forfeit their money for "non-performance"; and once a valid arbitral award has been passed, courts have very limited power to overturn it just because they might have decided the facts differently.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case