M/s. Parsvnath Film City Ltd. v. Chandigarh Administration
Background
Chandigarh Administration selected Parsvnath Film City Ltd. as the developer for a large Multimedia-cum-Film City project after competitive bidding, and the parties signed a Development Agreement in March 2007 under which the company paid Rs. 47.75 crore (25% of the bid price) upfront. The project stalled because the Administration took 16.5 months to hand over a demarcation plan for the site and never removed high-tension power lines running through it, making it impossible for the company to begin construction; when talks to resolve the impasse went nowhere, the company declared the agreement frustrated, and the Administration then terminated the contract, blaming the company and forfeiting the entire upfront payment.
Decision Breakdown
The Supreme Court restored (with modifications) the Arbitral Tribunal's award, which had already found the delay was caused by the Chandigarh Administration, not the developer, and had ordered the money refunded. The Punjab and Haryana High Court had wrongly set aside that award, incorrectly treating the developer as having unjustifiably abandoned the project. The Supreme Court held that under the Agreement's own terms, delay caused by the government side had to be excluded from the project timeline, that the government could not fault the developer for problems (encumbered land, undelivered demarcation plan) it had itself created and later admitted to in meetings, and that a court's power to interfere with an arbitral award is narrow. It cannot re-appreciate evidence or substitute its own view unless the award is genuinely against public policy or law. The Court upheld the refund of the Rs. 47.75 crore deposit and actual expenses, but reduced the interest rate from 12% to 8% per annum (rising back to 12% if payment wasn't made by a set deadline) and disallowed a separate compensation-for-loss amount as duplicative of the interest already awarded.
Lesson Learnt
When a government or public authority fails to deliver on its own contractual obligations (like handing over usable, encumbrance-free land on time) it cannot then blame the private party and forfeit their money for "non-performance"; and once a valid arbitral award has been passed, courts have very limited power to overturn it just because they might have decided the facts differently.