M/S Ravi Ranjan Developers Pvt. Ltd. vs Aditya Kumar Chatterjee

SLP (C) · 2022 INSC 1299Decided 24 Mar 2022
SLP (C) Nos. 17397-17398 of 2021
Indira Banerjee · A.S. Bopanna

Background

A developer (Ravi Ranjan Developers) and a landowner (Aditya Kumar Chatterjee) signed a Development Agreement in 2015 for property in Muzaffarpur, Bihar, which contained an arbitration clause stating that "the sitting of the said Arbitral Tribunal shall be at Kolkata." After a dispute arose and the landowner terminated the agreement, various proceedings were filed in Bihar (before RERA and the Muzaffarpur District Court), but the landowner also filed an application before the Calcutta High Court asking it to appoint an arbitrator. The developer objected that Calcutta had no jurisdiction since the property, the agreement's execution, and the parties' business were all in Bihar. The Calcutta High Court nonetheless appointed an arbitrator (recording that the developer's counsel had "agreed"), and later refused to review that order.

Decision Breakdown

The Supreme Court held that a defect of jurisdiction cannot be cured by a lawyer's consent, and can be challenged at any stage. On the core legal question, it clarified the difference between the "seat" of arbitration (which fixes exclusive court jurisdiction) and the mere "venue" for hearings: simply naming Kolkata as the place where the tribunal would "sit" only fixed a hearing venue, it did not make Kolkata the legal seat of arbitration or hand jurisdiction to the Calcutta High Court. Since the property, the agreement's execution and registration, the parties' residence/business, and the cause of action were all outside Calcutta's jurisdiction, the Calcutta High Court had no power to appoint an arbitrator. The Supreme Court set aside the Calcutta High Court's orders and, since arbitral sittings were nonetheless to occur in Kolkata, itself appointed a mutually agreed retired judge as the sole arbitrator.

Lesson Learnt

In an arbitration clause, merely naming a city as the place where hearings will be held does not automatically make that city the legal "seat" of arbitration or give its courts jurisdiction: parties should state clearly whether a named location is meant as the seat (which fixes which court can supervise the arbitration) or just a convenient venue for sittings.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case