M/s RKMT Buildcon Pvt Ltd Through Shri Kamal Singh, Director vs. Govt of NCT of Delhi PWD Through Executive Engineer, Education Division North West and connected matters
Background
RKMT Buildcon sought to enforce an arbitral award against the Delhi PWD relating to a school construction/maintenance contract. The stamp duty issue (payment beyond the permissible period) again arose. The same order also disposed of three connected petitions by the same petitioner against the same department (OMP (ENF.) (COMM.) 290/2025, 291/2025 and 292/2025).
Decision Breakdown
Applying the URC Construction precedent, the Court granted leave to withdraw the petition with liberty to refile after curing the defect, and dismissed the petition as withdrawn.
Lesson Learnt
Government contractors, no less than private commercial parties, must ensure timely stamping of arbitral awards before seeking court enforcement.