M/S Sanjay Iron Steel vs. Steel Authority Of India And Anr.

Original Miscellaneous Petition (Commercial) · 2026:DHC:7423Decided 2 Sept 2026New Delhi Bench
O.M.P. (COMM) 441/2024CNR: DLHC010716612024
Justice Om Prakash Shukla

Background

The petitioner had been appointed as SAIL's steel distributor for a cluster of dealers but, alleging SAIL itself was undercutting it by selling directly to customers at lower prices, tried to prematurely surrender its five-year distributorship and refused to renew its Rs. 1.28 crore performance bank guarantee (PBG). SAIL terminated the contract, encashed the PBG, and separately claimed over Rs. 2.3 crore in damages for the distributor's alleged breach; the arbitrator upheld the termination and PBG forfeiture but rejected SAIL's separate damages claim for lack of proof.

Decision Breakdown

The distributor argued it was inconsistent to forfeit its Rs. 1.28 crore guarantee while simultaneously finding SAIL hadn't actually proven any financial loss. The High Court disagreed, holding that the contract had two separate clauses: one letting SAIL recover proven losses/damages (which failed for lack of evidence), and a separate clause automatically letting SAIL forfeit the security/PBG whenever the contract was validly terminated for the distributor's failure to perform, with no requirement to first prove a specific loss. Since the distributor's breach and the termination's validity were themselves not challenged, the PBG forfeiture stood independently of the failed damages claim.

Lesson Learnt

A contract can validly have two different forfeiture mechanisms, one requiring proof of actual loss, and a separate automatic one triggered simply by termination for breach, so losing a damages claim for lack of proof doesn't automatically mean a separately-forfeited security deposit must be returned.

Arbitration & Commercial LawDelhi High Court

Gaurav Enterprises vs. Commissioner, Transport Department

Despite the Department's objection, the Court allowed the decree holder to withdraw its own petition, with liberty to file it again later if needed, subject to resolving any applicable stamp-duty requirements under the Indian Stamp Act, consistent with the Court's own precedent on that point.

Decided 12 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

CA Deepak Gupta vs. CA Shubham Jain

The Court sent the matter to the Delhi High Court's Mediation and Conciliation Centre (SAMADHAN) for three weeks, while simultaneously appointing a named Sole Arbitrator to take over if mediation fails, so the arbitration process can begin immediately without a second round of court proceedings, subject to the arbitrator's standard independence disclosures and the Delhi International Arbitration Centre's rules and fees.

Decided 12 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Freecharge Payment Technologies Pvt Ltd vs. Frederica Marketing Pvt Ltd

In light of the settlement, the Court allowed the decree holder to withdraw the enforcement petition, but expressly preserved its right to revive the same petition later if Frederica Marketing fails to honour the settlement's terms.

Decided 12 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Arcis Clean Energy Pvt. Ltd. v. Parshva Innovation

The Supreme Court examined the Agreement as a whole to determine which city was the true "juridical seat" of arbitration, as opposed to merely a convenient venue for hearings, and concluded, based on the Agreement's language and structure, that Goa was the juridical seat. Since the juridical seat determines which court has supervisory jurisdiction over the arbitration, the Court held that the Delhi High Court lacked jurisdiction to have entertained the Section 11(6) application in the first place. It set aside the High Court's order and left the parties free to pursue the correct remedy before the appropriate court.

Decided 12 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Hemant D. Shah HUF & Anr. v. Chittaranjan D. Shah HUF & Ors.

The Supreme Court held that whether someone is a "veritable party" to an arbitration, someone whose rights are substantially affected even without having signed the arbitration agreement, depends on the specific facts, and cannot be reduced to a rigid formula. On the facts here, it found the 3rd and 4th respondents to be veritable parties, since the validity of the 2009 partnership deed (and therefore their own rights) depended on whether the appellants' earlier retirement was itself valid. The Court made clear this finding was only a prima facie one for the purpose of deciding who should be part of the arbitration, and that the separate questions of limitation and estoppel raised by those respondents remain fully open for the Arbitral Tribunal itself to decide.

Decided 12 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Union of India vs. Swadeshi Civil Infrastructure Pvt. Ltd.

The Court upheld the bonus award, holding that a contractual clause excluding certain delay-extension grounds from bonus eligibility only barred the contractor from claiming "damages" for those delays, not from earning the bonus if the project still finished ahead of schedule. It also declined to interfere with the tribunal's GST-reimbursement direction, since it merely required reimbursement where GST was actually payable. However, it set aside the interest awarded on a separate claim because the contractor had never actually asked for interest on that specific claim, making that part of the award legally invalid and severable from the rest.

Decided 12 Oct 2026Read case