M/S S.D. Shinde Tr. Partner vs Govt. of Maharashtra & Ors.
Background
A contractor was awarded a road/canal construction contract by the Maharashtra Irrigation Department in 1983, but disputes over payment for additional and extra work led to arbitration. The arbitrator awarded the contractor over Rs. 1.5 crore plus interest and rejected the State's counter-claim, but the trial court set aside the award for "legal misconduct," holding the claim time-barred and beyond the arbitrator's mandate; the Bombay High Court upheld this. The contractor then appealed to the Supreme Court.
Decision Breakdown
The Supreme Court held that the claim was not time-barred because, per settled law (Inder Singh Rekhi and J.C. Budhraja), limitation in such contract disputes runs from when the final bill is prepared and a genuine dispute (claim followed by denial) arises: here the final bill was issued only in December 1992, so the 1995 arbitration request was within time. It also rejected the State's arguments about a 30-day contractual bar and about defective proceedings due to non-joinder of the deceased contractor's heirs, and found that a court's jurisdiction under Sections 30/33 of the old Arbitration Act is narrow. It can only interfere for an "error of law apparent on the face of the award," not re-appreciate facts, and here the arbitrator's award disclosed no such error. It therefore set aside the trial court and High Court judgments and restored the arbitral award, directing full payment within eight weeks with costs to the appellant.
Lesson Learnt
Courts reviewing an arbitral award under the old Arbitration Act cannot act as an appellate forum re-examining evidence. They may intervene only for a clear error of law visible on the face of the award itself; and in contract-payment disputes, the limitation clock generally starts running only once the final bill is prepared and the claim is actually disputed, not from the original contract completion date.