M/s. Shree Vishnu Constructions vs The Engineer in Chief, Military Engineering Service & Ors.

Civil Appeal · 2023 INSC 508Decided 9 May 2023
Civil Appeal No. 3461 of 2023
M.R. Shah · C.T. Ravikumar

Background

Shree Vishnu Constructions had a 2010 construction contract with the Military Engineering Service. After the final bill was paid in 2013 and the contractor issued a "no further claim" certificate, it later sent a notice in December 2013 invoking the contract's arbitration clause anyway. When the government did not act, the contractor applied to the Telangana High Court in 2016 to have an arbitrator appointed. The High Court refused, holding that because full and final payment had already been accepted with a no-claim certificate ("accord and satisfaction"), there was no live dispute to arbitrate, and it examined this question in detail rather than confining itself only to checking whether an arbitration agreement existed. The contractor argued this was wrong because, under the 2015 Amendment Act (which restricts courts at the Section 11 stage to only checking whether an arbitration clause exists, leaving all other issues to the arbitrator), the High Court should not have gone into "accord and satisfaction" at all.

Decision Breakdown

The key question was whether the pre-2015 law or the amended 2015 law applied, given that the arbitration notice was sent in 2013 (before the amendment) but the court application was filed in 2016 (after it). The contractor relied on the Supreme Court's BCCI vs Kochi Cricket ruling, which held the 2015 Amendment applies to all court proceedings begun after the amendment date, regardless of when the underlying arbitration was invoked. The Supreme Court held that BCCI's reasoning was specifically about Sections 34 and 36 (challenging and enforcing awards), not Section 11 (appointing arbitrators), and that the applicable, more specific precedents for Section 11 applications (Parmar Construction and Pradeep Vinod Construction) correctly held that when the arbitration notice pre-dates the 2015 Amendment, the case is governed by the old, pre-amendment law, even if the Section 11 application itself is filed later. Applying the old law, the High Court was right to examine and decide the "accord and satisfaction" question itself, and its finding that the dispute had already been finally settled was upheld. The appeal was dismissed.

Lesson Learnt

In arbitration disputes, the date you first send your notice invoking arbitration (not the date you later go to court asking for an arbitrator to be appointed) can determine which version of the arbitration law applies, so parties should be aware that older disputes may still be governed by rules that give courts wider power to screen out settled or non-existent disputes before appointing an arbitrator.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case