M/S Shriram EPC Limited v. Rioglass Solar SA

Civil Appeal · 2018 INSC 816Decided 13 Sept 2018
Civil Appeal No. 9515 of 2018
Justice Rohinton Fali Nariman · Justice Indu Malhotra

Background

Rioglass Solar SA obtained an ICC arbitral award in London against Shriram EPC Limited for breach of a supply agreement, directing Shriram to pay over €4.3 million in damages and interest. When Rioglass sought to enforce this foreign award in the Madras High Court, Shriram objected that the award could not be enforced because it had not been stamped under the Indian Stamp Act, 1899. A single judge of the Madras High Court rejected this objection and allowed enforcement, and an appeal to the Division Bench was held not maintainable, leading Shriram to approach the Supreme Court.

Decision Breakdown

The Supreme Court traced the history of arbitration and stamp legislation in India from 1899 onward and held that the term "award" in Item 12 of Schedule I of the Indian Stamp Act, 1899 has always meant only a domestic award made within British India/India, and never included foreign awards, since the Act's definition was never amended to bring in foreign awards even after the 1937, 1961 and 1996 arbitration enactments. As a fiscal statute, any ambiguity had to be resolved in favour of the party liable to pay the duty. The Court therefore held that a foreign award is not liable to Indian stamp duty at all, rejected arguments based on the New York Convention's "no more onerous conditions" clause (since that clause only applies if stamp duty is leviable in the first place) and on the Law Commission's 194th Report, and dismissed Shriram's appeal, upholding enforcement of the foreign award.

Lesson Learnt

A foreign arbitral award being enforced in India cannot be resisted on the ground that it lacks an Indian stamp: Indian stamp duty law has never covered foreign awards, so this is not a valid defence to enforcement.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case