M/s Tulsi Narayan Garg v. The M.P. Road Development Authority, Bhopal & Ors.

Civil Appeal · 2019 INSC 981Decided 30 Aug 2019
Civil Appeal Nos. 6726-6729 of 2019
Justice N.V. Ramana · Justice Indira Banerjee · Justice Ajay Rastogi

Background

The appellant, a registered Class 'A' contractor, was awarded contracts under the Pradhan Mantri Gram Sadak Yojana for construction of two rural roads in Madhya Pradesh. After the M.P. Road Development Authority terminated the agreements for alleged slow progress and claimed liquidated damages, the appellant challenged this, and was granted liberty to pursue arbitration before the Madhya Pradesh Arbitral Tribunal, where the dispute over the termination and damages remained pending. While that arbitration was still unresolved, the Authority nonetheless issued recovery notices and sought to recover the claimed damages as arrears of land revenue, which the appellant challenged before the Madhya Pradesh High Court, but the High Court upheld the Authority's right to recover.

Decision Breakdown

The Supreme Court held that under the contract's own dispute-resolution clauses, any determination of liquidated damages by the Authority's General Manager was subject to challenge through arbitration before the Arbitral Tribunal, and since a reference on precisely this dispute was already pending there, the Authority could not simultaneously act as judge in its own cause and initiate coercive recovery under the Land Revenue Act before the arbitration concluded. The Court relied on its own prior precedent holding that recovery of a disputed amount cannot be enforced through land revenue recovery procedures while the underlying liability is still sub judice before an arbitrator. Accordingly, the Court allowed the appeals, quashed the High Court's judgments upholding the recovery proceedings, and set aside the recovery notices, while clarifying that the Arbitral Tribunal remains free to decide the pending reference on liquidated damages independently, uninfluenced by any of the Supreme Court's observations.

Lesson Learnt

A government authority (or any contracting party) cannot use coercive recovery mechanisms like the Land Revenue Act to collect a disputed sum while that very dispute is still pending before an arbitrator: it must await the outcome of arbitration before enforcing recovery, since it cannot be the final judge of its own claim.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case