M/S Unibros vs All India Radio
Background
Unibros, a contractor, was awarded a construction contract by All India Radio for a building in Delhi that was supposed to finish in 12 months but was delayed by about 42.5 months due to the respondent's fault. An Arbitrator twice awarded Unibros roughly Rs. 1.44 crore for "loss of profit" during the delay period, calculated using Hudson's formula, but the Delhi High Court (both the Single Judge and the Division Bench) set aside this part of the award both times, finding that Unibros had produced no real evidence to prove it had actually lost profitable opportunities because of the delay. Unibros appealed to the Supreme Court, arguing that courts have very limited power to interfere with an arbitrator's factual findings and that Hudson's formula is a legally accepted method for calculating such losses.
Decision Breakdown
The Supreme Court held that while courts indeed have limited scope to interfere with arbitral awards, an award based on no evidence at all is "patently illegal" and conflicts with the fundamental public policy of India, which is a valid ground to set it aside under Section 34 of the Arbitration and Conciliation Act. The Court clarified that a claim for loss of profit due to delay requires the claimant to prove, with credible independent evidence (such as other projects declined, tendering opportunities lost, or financial records), that it actually had a viable alternative opportunity to earn profit elsewhere: a bare formula like Hudson's estimates the amount of loss but cannot itself substitute for proof that a loss occurred. Since Unibros never produced such evidence in either round of arbitration, the Court upheld the setting aside of the loss-of-profit award and dismissed the appeal, though it waived the costs earlier imposed by the Single Judge.
Lesson Learnt
A contractor cannot recover damages for "loss of profit" from a delayed contract simply by applying a standard formula; they must independently prove, with real evidence, that they actually lost a specific profitable opportunity because their resources were tied up: an arbitral award granting such damages without any such proof can be struck down as legally unsustainable.