M/S Vidyawati Construction Company v. Union of India
Background
Vidyawati Construction Company had a railway construction contract with the Union of India that called for a three-member arbitral tribunal, but after various procedural twists the High Court's Chief Justice ultimately appointed a single retired judge as sole arbitrator. Both sides' lawyers recorded, at a hearing in December 2003, that they agreed the sole arbitrator would proceed, and the Union of India then filed its statement of defence. Only months later, in April 2004, did it raise an objection that the tribunal's composition was invalid because the contract required three arbitrators; the sole arbitrator rejected this, but a District Court and later the High Court set aside the resulting award purely on this jurisdictional ground.
Decision Breakdown
The Supreme Court held that Section 16(2) of the Arbitration Act requires any objection to a tribunal's jurisdiction to be raised no later than the statement of defence, and here, the Union of India had expressly agreed to the sole arbitrator's appointment and filed its defence without objection, only raising the composition challenge afterward. That conduct amounted to submission to the sole arbitrator's jurisdiction, making the later objection time-barred and wrongly entertained by the Section 34 and Section 37 courts. The Court set aside the High Court and District Court judgments, restored the original Section 34 challenge to the District Court for it to decide the other grounds that had never actually been considered, while making clear the jurisdiction issue itself is now closed.
Lesson Learnt
In arbitration, a party that agrees to an arbitrator's appointment and files its defence without objecting to the tribunal's composition cannot ambush the process with a jurisdictional challenge later: such objections must be raised at the very first opportunity, or they are lost.