Municipal Corporation of Greater Mumbai v. M/S R.V. Anderson Associates Limited

Civil Appeal · 2026 INSC 228Decided 11 Mar 2026
C.A. No.-003277-003278 - 2026
Justice J.K. Maheshwari · Justice Atul S. Chandurkar

Background

The Municipal Corporation of Greater Mumbai (MCGM) had engaged a Canadian engineering firm, R.V. Anderson Associates Ltd., under a 1995 World Bank-funded contract to upgrade Mumbai's sewerage operations. After completion of work in 2001, a payment dispute arose, and the firm invoked arbitration in 2005. An Arbitral Tribunal ultimately ruled in favour of the firm in 2010, and MCGM's later attempts to have that award set aside failed before a Single Judge and then a Division Bench of the Bombay High Court, prompting this appeal to the Supreme Court solely on the ground that the Arbitral Tribunal itself had been improperly constituted (the third/presiding arbitrator, MCGM argued, should have been appointed by the Secretary General of ICSID rather than by the two party-nominated arbitrators).

Decision Breakdown

The Supreme Court held that the contractual clause referring to ICSID appointment was an enabling provision triggered only if a party actually approached ICSID, not a mandatory requirement, and since neither party had done so, the Co-Arbitrators were entitled to appoint the presiding arbitrator. More importantly, the Court found that MCGM had, over several years and on at least three occasions, been informed of and had acquiesced in the Co-Arbitrators appointing the presiding arbitrator without ever objecting, only raising the jurisdictional challenge for the first time years later, just before filing its statement of defence. The Court held that a party's conduct and acquiescence over time is a powerful indicator of how it actually understood the contract, and cannot be undone by belatedly invoking a jurisdictional objection under Section 16 of the Arbitration Act. Finding no infirmity in the concurrent findings of the Single Judge and Division Bench, the Court dismissed the appeals and upheld the arbitral award, with no order as to costs.

Lesson Learnt

A party that stays silent and participates in a process for years despite knowing of an alleged procedural defect cannot later spring that defect as a technical objection to escape an unfavourable outcome: conduct and acquiescence carry real legal weight in how courts interpret contested contractual terms.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case