National Bank Limited v. Ghanshyam Das Agarwal & Ors.

Civil Appeal · Neutral citation not assigned (Civil Appeal No. 7513 of 2009)Decided 14 Jan 2015
Civil Appeal No. 7513 of 2009
Justice Vikramajit Sen · Justice Arun Mishra

Background

An exporter of rice (the plaintiff) shipped a consignment to an importer in Bangladesh under a Letter of Credit (LC) opened by the appellant bank. The appellant bank received the shipping documents, flagged some discrepancies, but then, without informing the exporter or the negotiating bank, gave certified photocopies of the documents to the importer, who used them (allegedly with a forged clearance) to take delivery of the goods without the LC payment ever being made. The Calcutta High Court held the bank liable and decreed a money claim of USD 352,250 in the exporter's favour, which the bank appealed.

Decision Breakdown

The Supreme Court held that a bank opening a Letter of Credit bears a strict, fiduciary responsibility to ensure payment is secured before any consignment is released, and here the appellant bank's own written statement filed in a related Bangladeshi ("Dhaka") suit amounted to a clear admission that it was obligated to reimburse the exporter's bank. The Court found the appellant bank's conduct, certifying photocopies to the importer without safeguards and allowing the goods to be released without payment, was a clear breach of this fiduciary duty, regardless of whether it was complicit in the forgery used by the importer. Since an interim order had already allowed the impugned judgment to operate and the LC funds had already left the bank's control, the Court held the appeal to be essentially without merit and dismissed it with costs.

Lesson Learnt

A bank that opens a Letter of Credit for international trade carries a strict duty to protect the exporter's right to payment: it cannot hand over shipping documents or facilitate release of goods to the buyer without ensuring the agreed payment has been secured, and its own admissions in related litigation can be used against it.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case