National Highway Authority of India v. M/s. ProgressiveMVR (JV)

Civil Appeal · 2018 INSC 195Decided 23 Feb 2018
Civil Appeal No. 458 of 2018
Justice A.K. Sikri · Justice Ashok Bhushan

Background

NHAI's standard construction contracts contain a price-adjustment formula (Clause 70.3) meant to compensate contractors for rises or falls in the cost of materials like bitumen, cement and steel during the life of a project. A dispute arose over whether the percentage-weight of each material in that formula should be calculated using the "base rate" (the price fixed 28 days before the bid was submitted) or the "current rate" (the price in the month the work was actually billed). Different Arbitral Tribunals, across this and connected appeals involving the same NHAI contract terms, had reached conflicting answers, some favouring the contractors' current-rate approach and some favouring NHAI's base-rate approach, and the matter reached the Supreme Court through three connected civil appeals.

Decision Breakdown

The Supreme Court held that the base rate (fixed 28 days before the bid) must be used to calculate the percentage weight of bitumen, cement and steel in the price-adjustment formula, not the fluctuating current rate, reasoning that using current rates could even produce an absurd "negative" material percentage, and that the formula already compensates contractors for price rises through a separate component of the same clause. Because this interpretation showed the Arbitral Tribunals had misapplied the formula, the resulting awards were held contrary to the contract terms. The Court made its ruling binding on all pending cases raising the same clause-interpretation dispute (though not on awards that had already finally attained closure), allowed all three appeals, and set aside both the High Court's judgment and the Arbitral Tribunal's award on the bitumen price-adjustment claim, with no order as to costs.

Lesson Learnt

Where multiple arbitral tribunals interpret the identical contract clause in conflicting ways across similar disputes, a court can step in to settle the correct interpretation definitively rather than treating each conflicting award as an equally "plausible view" immune from interference, and that settled interpretation will bind other pending (not yet finally concluded) disputes over the same clause.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case