National Highway Authority of India vs Transstroy (India) Limited

Civil Appeal · 2022 INSC 680Decided 11 Jul 2022
Civil Appeal No. 6732 of 2021
M.R. Shah · Sanjiv Khanna · B.V. Nagarathna as the second judge

Background

NHAI and the contractor, Transstroy, entered into a highway construction contract in Tamil Nadu. After alleging repeated breaches by the contractor, NHAI issued a cure-period notice and eventually terminated the contract, expressly reserving its right to claim damages. The contractor then invoked arbitration, and NHAI, in its statement of defence, again reserved its right to file a counter-claim separately and later sought an extension of time to formally file it. The Arbitral Tribunal refused to allow NHAI's counter-claim, holding it was beyond the scope of the arbitration since NHAI had not followed the contract's amicable-settlement/conciliation procedure (Clauses 26.1 and 26.2) before raising it, and the Delhi High Court upheld this refusal in a challenge under the Arbitration Act.

Decision Breakdown

The Supreme Court held that the Arbitral Tribunal and the High Court had wrongly conflated a "claim" (raised by one party) with a "Dispute" (which, by definition, has two sides). Once a dispute (here, the termination of the contract) is validly notified and taken to arbitration after the conciliation clauses fail, the entire subject matter, including any counter-claim or set-off connected to that dispute, falls within the scope of the arbitration under Section 23(2A) of the Arbitration Act. Since NHAI had consistently and from the outset reserved its right to raise a counter-claim (including in its termination notice and statement of defence) and there was no real delay attributable to it, refusing to let it file the counter-claim would defeat the very purpose of Section 23(2A) and could lead to a multiplicity of parallel proceedings over the same underlying transaction. The Court set aside both the Tribunal's and the High Court's orders, allowed NHAI to file its counter-claim for adjudication alongside the contractor's claims, and excluded the period lost due to the litigation (18.07.2017 to 11.07.2022) from the statutory time limit for the Tribunal to pass its award.

Lesson Learnt

In arbitration arising from a single underlying dispute (such as a contract termination), a party's counter-claim connected to that dispute generally falls within the tribunal's jurisdiction and should not be shut out on narrow technical grounds, doing so risks forcing parties into duplicate, piecemeal litigation over what is really one dispute.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case