National Highways Authority of India v. M/S JSC Centrodorstroy

Civil Appeal · Neutral citation not assigned (Civil Appeal No. 2529 of 2016)Decided 18 Apr 2016
Civil Appeal No. 2529 of 2016
Justice Dipak Misra · Justice Uday Umesh Lalit

Background

NHAI had awarded a highway construction contract to the respondent, a foreign contractor, which included a "Subsequent Legislation" clause (Clause 70.8) allowing additional costs caused by new or changed laws after the bid date to be added to the contract price. The respondent claimed additional costs arising from increases in service tax on its insurance premium and on bank guarantee charges for the project, and the Arbitral Tribunal awarded these amounts in the respondent's favour. NHAI's challenge to the award was dismissed by a Single Judge and then by a Division Bench of the Delhi High Court, leading to this appeal (along with a second, near-identical appeal concerning a different contract with the same respondent).

Decision Breakdown

The Supreme Court noted that similar COPA clauses had already been interpreted in NHAI v. ITD Cementation India Ltd., where a comparable arbitral view was upheld. NHAI argued that costs like bank guarantee service tax should be excluded because furnishing a bank guarantee was optional, but the respondent showed that an unconditional bank guarantee had in fact become a mandatory contractual requirement. The Court reiterated the settled principle that interpretation of contract terms is primarily for the arbitrator, and courts should not interfere unless the arbitrator's view is one no fair-minded or reasonable person could take. Finding the Arbitral Tribunal's view that the service tax increases were linked to the contract's performance terms to be a reasonable, possible interpretation, the Court held there was no merit in NHAI's appeals and dismissed both without costs.

Lesson Learnt

Courts give significant deference to an arbitrator's interpretation of contract terms; a party challenging an arbitral award cannot succeed merely by offering an alternative reading of the contract: it must show the arbitrator's view was one no reasonable person could have reached.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case