National Highways Authority of India vs. M/s Hindustan Construction Company Ltd.

Not available · 2024 INSC 388Decided 7 May 2024
Not available
Justice Abhay S. Oka · Justice Pankaj Mithal

Background

NHAI had awarded a road construction contract to the respondent for the Allahabad Bypass Project worth over Rs. 446 crore. Disputes arose over three claims: extra costs from increased royalty and sales tax on construction materials, non-payment for embankment work involving initial soil stripping, and extra costs from increased forest transit fees, and these went to arbitration. An Arbitral Tribunal ruled substantially in the contractor's favour on all three claims (with a 2-1 majority on the embankment claim), awarding several crores with interest. NHAI's challenges to the award were rejected first by a Single Judge and then by a Division Bench of the Delhi High Court, leading to this batch of appeals before the Supreme Court.

Decision Breakdown

The Supreme Court reiterated that courts have only a narrow scope to interfere with arbitral awards under Section 34 of the Arbitration Act, and an even narrower scope on appeal under Section 37. They cannot act as an appellate court re-examining facts, and must respect a reasonable interpretation of contract terms by the Arbitral Tribunal even if another view were possible. On the royalty and tax claims, the Court found the issue was already settled by an earlier Supreme Court decision (NHAI v. ITD Cementation) involving identical contract clauses, which held that additional costs from later legislation/tax changes are payable separately from the standard price-adjustment formula. On the embankment claim, since two of the three arbitrators (the technical experts) had ruled in the contractor's favour and their reasoning was not shown to be perverse or illegal, the Court declined to disturb that majority finding. Finding no merit in NHAI's challenge on any point, the Supreme Court dismissed all the connected appeals with no order as to costs.

Lesson Learnt

Courts will not re-open the merits of an arbitration award or substitute their own view for a reasonable interpretation the arbitrators gave to a contract: a party unhappy with an award needs to show the ruling is illegal or perverse, not merely arguable the other way.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case