National Projects Construction Corporation Ltd. v. Ishvakoo (India) Pvt. Ltd.

Civil Appeal · 2026 INSC 828Decided 11 Aug 2026
Civil Appeal No. 5819 of 2025
Justice K.V. Viswanathan · Justice Alok Aradhe · Justice Arun Palli

Background

The two companies had a 2002 agreement for bus terminus and heritage-corridor works in Agra, under which Ishvakoo received a Rs. 3.5 crore mobilisation advance backed by bank guarantees. After disputes went to arbitration, National Projects invoked and encashed the bank guarantees in 2017 because Ishvakoo failed to keep them alive as it had undertaken to the Delhi High Court back in 2005. The arbitrator later dismissed Ishvakoo's claims (including for discharge of the guarantees), but did not address whether the guarantee amount should nonetheless be returned once the underlying advance was found to have been used. Ishvakoo then went to the High Court under Section 9 seeking return of the Rs. 3.5 crore pending its Section 34 challenge to the award, and won at both the Single Judge and Division Bench stage.

Decision Breakdown

The Supreme Court examined whether an unsuccessful party in arbitration (an "Award Debtor" of sorts, here really the losing claimant) can even seek Section 9 interim relief after losing, and relied on its recent ruling in Home Care Retail Marts v. Haresh N. Sanghavi holding that such relief is legally permissible in rare and compelling cases, though subject to a higher threshold. Applying that standard, the Court found several factors favoured Ishvakoo: no counter-claim had ever been filed by National Projects, the arbitrator's findings did not actually decide whether Ishvakoo was entitled to discharge of the guarantees, and the arbitrator appeared unaware the guarantees had already been encashed before the award was even passed. Since letting National Projects keep the money pending the Section 34 challenge would amount to unjust enrichment and would also conflict with the 2005 High Court order's own terms, the Supreme Court held the High Court had properly exercised its Section 9 discretion. The appeal was dismissed, and National Projects was directed to deposit Rs. 3.5 crore with the High Court Registry within four weeks, to be kept in an interest-bearing fixed deposit until the Section 34 proceedings are decided.

Lesson Learnt

Even a party that has lost in arbitration can, in rare and compelling cases, still seek interim protection from the courts (under Section 9) while its challenge to the award is pending, losing an arbitration does not automatically leave a party without any interim remedy, especially where allowing the other side to keep disputed money would amount to unjust enrichment.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case