New India Assurance Co. Ltd. v. Genus Power Infrastructure Ltd.
Background
After a fire damaged its factory, an insured company accepted about ₹5.96 crore and signed a detailed full settlement and subrogation letter. Nearly three weeks later, it alleged coercion and financial pressure and sought arbitration for additional compensation. The High Court appointed an arbitrator, leaving the settlement objection to that arbitrator.
Decision Breakdown
The Supreme Court allowed the insurer's appeal and set aside the appointment order. Applying the appointment-stage approach in this 2014 judgment, it found the coercion allegation lacked details or supporting material. The absence of a contemporaneous protest and the company's financial circumstances supported a finding that the settlement had been voluntary. Because the claim had been fully settled, no arbitrable dispute remained for appointment under Section 11. The Court recognised that a genuinely involuntary discharge could be challenged, but found that this company's bare allegations did not establish one.
Lesson Learnt
A full settlement cannot be reopened merely by later asserting financial pressure without credible supporting facts. Anyone alleging coercion should preserve evidence and raise a clear, timely objection; this judgment applied the arbitration appointment procedure then in force.