New Okhla Industrial Development Authority & Ors. v. M/s Sunshine Trade Tower Pvt. Ltd. & Anr.

Civil Appeal · 2026 INSC 975Decided 8 Sept 2026
Civil Appeal Nos. 10900-10902 of 2025
Justice Pamidighantam Sri Narasimha · Justice Alok Aradhe

Background

NOIDA allotted a commercial plot to a developer in 2012 for a large sale consideration, promising access via a 45-metre "Front Road" and a 24-metre "Side Road" as per the sanctioned site plan. The 45-metre road was never built because it ran over encroached, unacquired inhabited land, and the 24-metre road wasn't completed until 2020. The developer sought the benefit of NOIDA's "Zero Period Policy" (which pauses lease-rental instalments when access is unavailable), but NOIDA repeatedly refused despite its own Tehsildar, a revenue authority (UPRERA), and the State Government's revisional orders confirming the access road was genuinely blocked.

Decision Breakdown

The Supreme Court held that policy clauses like the Zero Period Policy must be interpreted purposively, not like a rigid statute, and that its purpose was to ensure a developer has "easy, effective, and legitimate" access to build, not to be defeated merely because some partial or difficult access technically existed. Given five separate official reports and orders all confirming the 45-metre Front Road was never actually provided, NOIDA's persistent refusal to extend Zero Period benefits and to sanction a revised site plan (treating the 24-metre road as the new frontage) was unreasonable and untenable. The Court dismissed NOIDA's appeals and upheld the Allahabad High Court's judgment directing the Zero Period benefit and approval of the revised plan, recording the developer's undertaking to complete the project within four years.

Lesson Learnt

A public development authority cannot enforce strict contractual timelines and demand full payment from an allottee while itself failing to deliver the promised infrastructure (like access roads). Official reports confirming non-performance by the authority carry decisive weight, and relief policies meant to protect developers from such default must be applied purposively rather than technically.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case