North Eastern Electric Power Corporation Limited (NEEPCO) v. Astra Construction Private Limited

Civil Appeal · 2026 INSC 1036Decided 22 Sept 2026
Civil Appeal arising out of SLP(C) No. 24803 of 2025
Justice Pamidighantam Sri Narasimha · Justice Alok Aradhe

Background

NEEPCO had engaged Astra Construction for civil works on a power project in Tripura in the 1990s; disputes arose and went to arbitration, where the Tribunal found the delay attributable to NEEPCO, awarded the contractor about Rs. 3.30 crore, plus pre-reference interest at 12% and further pendente lite/future interest at 9%. The Commercial Court, relying on Clause 54 of the contract's General Conditions and Supreme Court precedent (Sayeed Ahmed), struck down the pre-reference and pendente lite interest as barred by contract. The High Court of Meghalaya reversed this, holding Clause 54 was worded like the clause in an older case (Harish Chandra) which did not bar interest, and restored the Tribunal's full interest award, leading NEEPCO to appeal to the Supreme Court, challenging only the pre-reference interest portion.

Decision Breakdown

The Supreme Court undertook a close textual comparison of contract clauses across several precedents and held that Clause 54 was materially different from the clause in Harish Chandra: while that older clause barred interest only on money withheld "because of a dispute," Clause 54 separately and independently also barred interest for mere "delay... in making periodical or final payments," irrespective of any dispute. A structure matching the clauses in Sayeed Ahmed and THDC-II, both of which were held to be complete bars on arbitral interest. The Court reaffirmed that under the 1996 Act, unlike the 1940 Act, an express contractual bar on interest (even a general one, not aimed specifically at the arbitrator) is enough to exclude the Tribunal's power under Section 31(7)(a), and pre-reference interest specifically depends on substantive law/agreement, not on Section 31(7)(a) alone. It also rejected the argument that NEEPCO had waived this defence, since the plea was on record from its original written statement before the Tribunal. The Court therefore set aside the High Court's restoration of pre-reference interest and allowed the appeal to that extent.

Lesson Learnt

In government/PSU contracts, the exact wording of a "no interest" clause is decisive. A clause that separately bars interest for mere payment delay (not just disputed amounts) can validly block an arbitrator from awarding pre-reference interest, so contracting parties should read such boilerplate clauses carefully before assuming interest will automatically follow a favourable award.

Arbitration & Commercial LawSupreme Court of India

Shreeram Builders v. Upendra Kantilal Thanawala & Ors.

The Supreme Court upheld setting aside the award, though for more precise reasons, holding that stamp duty classification alone wasn't decisive, but the arbitrators had exceeded their authority by effectively rewriting the contract: the price was never fixed, full consideration was never paid by deadline, and the arbitrators invented an unexplained price multiplier and damages the contract never provided for. Invoking its Article 142 power to do complete justice, the Court ordered the owners to refund all amounts received from the builder with 9% interest, since they never returned the payments after terminating the deal.

Decided 29 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S S.R. Ashok & Associates vs. Delhi Development Authority & Anr. and connected matters

The Court rejected the time-bar argument since the arbitration invocation was a single continuing one and DDA had consented to delays while participating throughout. It found no error apparent on the face of either award, upholding both and making them enforceable court decrees.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Axis Finance Ltd vs. Mr Nikhil A V & Ors.

The Court granted leave and liberty to withdraw and dismissed the petition without ruling on the underlying dispute.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

MMTC Limited vs. Aust Grain Exports Pty Ltd

The Court rejected MMTC's procedural and compensation arguments but found one real flaw: the tribunal had expressly rejected the exporter's claim for interest on the refunded guarantee (since the contract barred it), yet then awarded that very interest anyway, a direct, unexplained contradiction. The Court struck out only that contradictory portion as severable, leaving the rest of the award intact.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Chief Electoral Officer & Anr. vs. M/S Mahlakshmi Light House

The government argued the arbitrator ignored an internal inquiry suggesting inflated bills. The Court held returning officers who checked goods at the time gave more reliable evidence than a later inquiry report, and this specific objection was never raised before the single judge, so couldn't be raised for the first time on appeal. The appeal was dismissed.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Utracon Corporation Pte Ltd vs. Ucon PT Structural System Private Limited (formerly Utracon Structural Systems Private Limited) & Ors.

The defendant applied to refer the whole suit to arbitration, arguing the real dispute was about contractual rights to use the marks between identified parties (not a trademark registration or grant dispute, which can't be arbitrated), flowing from a single composite transaction. The Court agreed: the arbitration clause's existence was undisputed, the dispute was essentially contractual, and since the plaintiff itself had pleaded that the other defendants formed a "single economic unit" with the main defendant and derived their rights "through" it, their claims couldn't be separated out either; any question of whether they were bound by the arbitration clause was for the arbitrator to decide. The Court referred the whole suit to arbitration and disposed of it, expressly offering no opinion on the merits.

Decided 28 Oct 2026Read case