North Eastern Electric Power Corporation Limited (NEEPCO) v. Astra Construction Private Limited

Civil Appeal · 2026 INSC 1036Decided 22 Sept 2026
Civil Appeal arising out of SLP(C) No. 24803 of 2025
Justice Pamidighantam Sri Narasimha · Justice Alok Aradhe

Background

NEEPCO had engaged Astra Construction for civil works on a power project in Tripura in the 1990s; disputes arose and went to arbitration, where the Tribunal found the delay attributable to NEEPCO, awarded the contractor about Rs. 3.30 crore, plus pre-reference interest at 12% and further pendente lite/future interest at 9%. The Commercial Court, relying on Clause 54 of the contract's General Conditions and Supreme Court precedent (Sayeed Ahmed), struck down the pre-reference and pendente lite interest as barred by contract. The High Court of Meghalaya reversed this, holding Clause 54 was worded like the clause in an older case (Harish Chandra) which did not bar interest, and restored the Tribunal's full interest award, leading NEEPCO to appeal to the Supreme Court, challenging only the pre-reference interest portion.

Decision Breakdown

The Supreme Court undertook a close textual comparison of contract clauses across several precedents and held that Clause 54 was materially different from the clause in Harish Chandra: while that older clause barred interest only on money withheld "because of a dispute," Clause 54 separately and independently also barred interest for mere "delay... in making periodical or final payments," irrespective of any dispute. A structure matching the clauses in Sayeed Ahmed and THDC-II, both of which were held to be complete bars on arbitral interest. The Court reaffirmed that under the 1996 Act, unlike the 1940 Act, an express contractual bar on interest (even a general one, not aimed specifically at the arbitrator) is enough to exclude the Tribunal's power under Section 31(7)(a), and pre-reference interest specifically depends on substantive law/agreement, not on Section 31(7)(a) alone. It also rejected the argument that NEEPCO had waived this defence, since the plea was on record from its original written statement before the Tribunal. The Court therefore set aside the High Court's restoration of pre-reference interest and allowed the appeal to that extent.

Lesson Learnt

In government/PSU contracts, the exact wording of a "no interest" clause is decisive. A clause that separately bars interest for mere payment delay (not just disputed amounts) can validly block an arbitrator from awarding pre-reference interest, so contracting parties should read such boilerplate clauses carefully before assuming interest will automatically follow a favourable award.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case