NTPC Ltd. vs M/S SPML Infra Ltd.
Background
NTPC and SPML were in a contract dispute over Bank Guarantees that NTPC withheld even after SPML completed its work and received final payment. SPML went to the Delhi High Court seeking release of the guarantees; while that case was pending, the parties signed a Settlement Agreement in 2020 under which NTPC released the guarantees, SPML withdrew its case, and SPML agreed not to raise any further claims or seek arbitration. A few months after benefiting from the settlement, SPML reversed course, alleged the settlement had been signed under coercion and economic duress, and applied to the High Court to set up an arbitration tribunal to reopen the dispute. The High Court agreed and ordered arbitration; NTPC appealed to the Supreme Court.
Decision Breakdown
The Supreme Court held that when a court is asked under Section 11(6) of the Arbitration Act to appoint an arbitrator, it must undertake a limited "prima facie" screening and can refuse reference where the case is ex facie meritless or the dispute has already been genuinely settled. Examining the sequence of events, the Court found SPML's coercion claim to be an afterthought: SPML had made no coercion allegations while the Settlement Agreement was being negotiated or implemented, waited until it had reaped the settlement's benefits (getting the guarantees released and withdrawing its writ petition) before raising the plea, and never raised its large monetary claim during the life of the original contract. The High Court's order referring the matter to arbitration was set aside, and the appeal was allowed.
Lesson Learnt
A party cannot enjoy the benefits of a negotiated settlement and then, later, cry coercion to escape its terms and revive disputes it had agreed to give up. Courts will look at the real timeline of events, not just the label put on a claim, before allowing a dispute to go to arbitration.