Oil and Natural Gas Corporation Ltd. vs M/S G & T Beckfield Drilling Services Pvt. Ltd.

Not available · 2025 INSC 1066Decided 2 Sept 2025
Not available
Justice Pamidighantam Sri Narasimha · Justice Manoj Misra

Background

A three-member arbitral tribunal had awarded G&T Beckfield Drilling Services (a contractor) about USD 6,56,272 against ONGC for unpaid invoices, along with 12% annual interest running from the date the claim was affirmed (1998) until recovery. ONGC challenged the award, and a District Judge set it aside, but the Gauhati High Court restored the award in full. ONGC then appealed to the Supreme Court, but only on the narrow question of whether the 12% pre-award ("pendente lite") interest was validly awarded, given a contract clause (Clause 18.1) stating "no interest shall be payable by ONGC on any delayed payment/disputed claim."

Decision Breakdown

The Supreme Court held that an arbitral tribunal can be stripped of its power to award pendente lite (pre-award) interest only where the contract's wording explicitly or by necessary implication bars it: a clause that merely bars interest on "delayed payment" is not automatically read as also barring pendente lite interest. Surveying a long line of precedent (including G.C. Roy, the two Ambica Construction decisions, Reliance Cellulose, Sayeed Ahmed, and the Tehri Hydro Development Corporation cases), the Court found that Clause 18.1 only barred interest on delayed/disputed payments, not interest during the pendency of arbitration, and did not use the sweeping "in any respect whatsoever" language found in clauses that other judgments had held to be a full bar. Since the 12% rate was also reasonable (lower than the statutory 18% default), the Court upheld the award of pendente lite interest and dismissed ONGC's appeal.

Lesson Learnt

In arbitration contracts, a clause barring "interest on delayed payment" does not automatically bar interest for the period the dispute is pending before the arbitrator: parties who want to exclude pendente lite interest must say so in clear, comprehensive language, or an arbitrator will retain discretion to award it.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case