Pam Developments Private Limited vs. The State of West Bengal & Anr.
Background
A road-construction contractor completed a widening/strengthening project for the West Bengal government with some delay and raised multiple claims (loss of business, machinery costs, labour charges, interest on delayed payments, escalation, and interest on the award) before an arbitrator. The arbitrator awarded several claims; the District Judge partly upheld this under Section 34 of the Arbitration Act; the Calcutta High Court, under Section 37, further set aside some of the claims and modified the interest awarded.
Decision Breakdown
The Supreme Court held that a court reviewing an arbitral award under Sections 34/37 cannot substitute its own view for a plausible one taken by the arbitrator: interference is permitted only where the award is perverse or against public policy. It restored the arbitrator's award of interest on delayed running-account bill payments (claim 4) and pre-reference interest (claim 6), holding the High Court had wrongly re-appreciated the underlying facts. It upheld the setting aside of the claim for idle-labour/machinery costs (claim 3) since the contract's own "Special Terms and Conditions" expressly barred such claims.
Lesson Learnt
Courts have very limited power to second-guess an arbitrator's factual findings; and unless a contract expressly prohibits it, an arbitrator can award interest for the period before a dispute was formally referred to arbitration (pre-reference interest).