Rajendra Kumar Tekriwal v. M/s Unique Constrn. P. Ltd. & Ors.

Civil Appeal · Neutral citation not assigned (Civil Appeal No. 9555 of 2010)Decided 17 Feb 2016
Civil Appeal No. 9555 of 2010
Justice Kurian Joseph · Justice Rohinton Fali Nariman

Background

Rajendra Kumar Tekriwal and a construction company (Unique Construction) were in dispute over a matter already referred to and pending before an Arbitrator. A respondent (Respondent No. 3) had separately raised an objection before the Supreme Court that he was not a necessary party to the arbitration. The main appeal (CA 9555/2010) and a connected cross-appeal (CA 9556/2010) by Respondent No. 1 were both before the Court, along with a prior interim order dated 25.02.2010 restraining certain action pending the appeals.

Decision Breakdown

The Supreme Court held that since the Arbitrator was already seized of the dispute, it was for the Arbitrator, not the Court, to decide whether Respondent No. 3 was a necessary party. The Court dismissed both the main appeal and the cross-appeal and vacated the earlier interim order, while expressly clarifying that all parties remained free to raise their contentions before the Arbitrator and requesting the Arbitrator to conclude proceedings expeditiously, preferably within six months. The Court also protected the appellant's position going forward: if any party entered into a transaction in the interim, sale proceeds would remain subject to the arbitration's outcome, and the appellant retained the right to separately challenge any valuation dispute through appropriate legal action.

Lesson Learnt

When a dispute is already before an arbitrator, courts will generally decline to pre-decide procedural objections (like who is a necessary party) and will instead let the arbitrator rule on them, while still protecting the parties' interim financial position (e.g., tying sale proceeds to the arbitration outcome) so that no one is prejudiced by the delay.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case