Rajendra Kumar Tekriwal v. M/s Unique Constrn. P. Ltd. & Ors.
Background
Rajendra Kumar Tekriwal and a construction company (Unique Construction) were in dispute over a matter already referred to and pending before an Arbitrator. A respondent (Respondent No. 3) had separately raised an objection before the Supreme Court that he was not a necessary party to the arbitration. The main appeal (CA 9555/2010) and a connected cross-appeal (CA 9556/2010) by Respondent No. 1 were both before the Court, along with a prior interim order dated 25.02.2010 restraining certain action pending the appeals.
Decision Breakdown
The Supreme Court held that since the Arbitrator was already seized of the dispute, it was for the Arbitrator, not the Court, to decide whether Respondent No. 3 was a necessary party. The Court dismissed both the main appeal and the cross-appeal and vacated the earlier interim order, while expressly clarifying that all parties remained free to raise their contentions before the Arbitrator and requesting the Arbitrator to conclude proceedings expeditiously, preferably within six months. The Court also protected the appellant's position going forward: if any party entered into a transaction in the interim, sale proceeds would remain subject to the arbitration's outcome, and the appellant retained the right to separately challenge any valuation dispute through appropriate legal action.
Lesson Learnt
When a dispute is already before an arbitrator, courts will generally decline to pre-decide procedural objections (like who is a necessary party) and will instead let the arbitrator rule on them, while still protecting the parties' interim financial position (e.g., tying sale proceeds to the arbitration outcome) so that no one is prejudiced by the delay.