Raval Manharbhai Kalidas & Ors. v. Bhaskarbhai Chandubhai Patel & Ors.
Background
A scheme for administering a public trust (concerning Vasad village, District Anand, Gujarat, and the election of its managing body) had originally been framed by the Joint Charity Commissioner. The Gujarat High Court later modified that scheme, but the appellants objected that the affected villagers had not been given a chance to be heard before those modifications, only the counsel appearing for some parties in the High Court had been heard. On an earlier hearing (21 February 2017), the Supreme Court agreed that a public notice under Order I Rule 8 CPC should have been issued before such major changes, and directed the appellants to publish notice in two Gujarati newspapers giving villagers 10 days to respond, before listing the matter for final disposal.
Decision Breakdown
By the time of this order, the required public notice had been published, but no one appeared before the Supreme Court to raise any objection (though some objections had reportedly been filed before the Charity Commissioner separately). The Court held that, even independent of the notice issue, it was not inclined to interfere with the High Court's judgment, since the High Court had already considered all the objections and made the modifications in the best interests of the Trust. The appeals were accordingly dismissed, the interim stay earlier granted was vacated, and the Court allowed any villagers wishing to enroll to do so under the High Court's scheme by 10 April 2017, with trust elections to follow within four weeks.
Lesson Learnt
Even where a court order is challenged for a procedural defect (such as lack of public notice to affected persons), the challenge becomes moot if, once that defect is cured and the affected persons are given the opportunity to object, nobody actually comes forward: courts will not disturb a substantively sound decision over a procedural gap that caused no real prejudice once corrected.