S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

Enforcement Petition (Commercial Arbitration) · 2026:DHC:8938Decided 8 Oct 2026New Delhi Bench
OMP (ENF.) (COMM.) 56/2021CNR: DLHC010123432021
Justice Om Prakash Shukla

Background

S and P Infrastructure Developers, the decree holder, sought to enforce an arbitral award against the National Highways Authority of India (NHAI). The stamp duty on the award had been paid on 05.03.2021, more than a month after the award's execution. A Joint Registrar had earlier allowed the matter to proceed after the decree holder deposited the shortfall in stamp duty.

Decision Breakdown

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Lesson Learnt

Arbitral awards must be properly stamped within the statutory period at the time of execution: a delayed top-up payment of stamp duty, however well-intentioned, does not cure the defect, and enforcement petitions can be dismissed (with liberty to refile) until the stamping is done correctly.

Arbitration & Commercial LawSupreme Court of India

Shreeram Builders v. Upendra Kantilal Thanawala & Ors.

The Supreme Court upheld setting aside the award, though for more precise reasons, holding that stamp duty classification alone wasn't decisive, but the arbitrators had exceeded their authority by effectively rewriting the contract: the price was never fixed, full consideration was never paid by deadline, and the arbitrators invented an unexplained price multiplier and damages the contract never provided for. Invoking its Article 142 power to do complete justice, the Court ordered the owners to refund all amounts received from the builder with 9% interest, since they never returned the payments after terminating the deal.

Decided 29 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S S.R. Ashok & Associates vs. Delhi Development Authority & Anr. and connected matters

The Court rejected the time-bar argument since the arbitration invocation was a single continuing one and DDA had consented to delays while participating throughout. It found no error apparent on the face of either award, upholding both and making them enforceable court decrees.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Axis Finance Ltd vs. Mr Nikhil A V & Ors.

The Court granted leave and liberty to withdraw and dismissed the petition without ruling on the underlying dispute.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

MMTC Limited vs. Aust Grain Exports Pty Ltd

The Court rejected MMTC's procedural and compensation arguments but found one real flaw: the tribunal had expressly rejected the exporter's claim for interest on the refunded guarantee (since the contract barred it), yet then awarded that very interest anyway, a direct, unexplained contradiction. The Court struck out only that contradictory portion as severable, leaving the rest of the award intact.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Chief Electoral Officer & Anr. vs. M/S Mahlakshmi Light House

The government argued the arbitrator ignored an internal inquiry suggesting inflated bills. The Court held returning officers who checked goods at the time gave more reliable evidence than a later inquiry report, and this specific objection was never raised before the single judge, so couldn't be raised for the first time on appeal. The appeal was dismissed.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Utracon Corporation Pte Ltd vs. Ucon PT Structural System Private Limited (formerly Utracon Structural Systems Private Limited) & Ors.

The defendant applied to refer the whole suit to arbitration, arguing the real dispute was about contractual rights to use the marks between identified parties (not a trademark registration or grant dispute, which can't be arbitrated), flowing from a single composite transaction. The Court agreed: the arbitration clause's existence was undisputed, the dispute was essentially contractual, and since the plaintiff itself had pleaded that the other defendants formed a "single economic unit" with the main defendant and derived their rights "through" it, their claims couldn't be separated out either; any question of whether they were bound by the arbitration clause was for the arbitrator to decide. The Court referred the whole suit to arbitration and disposed of it, expressly offering no opinion on the merits.

Decided 28 Oct 2026Read case
S And P Infrastructure Developers (Pvt) Ltd vs. National…