Sanwarlal Agrawal & Ors. vs Ashok Kumar Kothari & Ors.

Civil Appeal · 2023 INSC 149Decided 21 Feb 2023
Civil Appeal Nos. 1312-1313 of 2023
Krishna Murari · S. Ravindra Bhat

Background

The Agrawal and Kothari groups were equal partners in a 2017 joint venture to run a multi-specialty hospital in Malad, Mumbai, each having advanced about Rs 10 crore as interest-free loans. In March 2019 the Kotharis bid Rs 36.75 crore for the Agrawals' 50% shareholding, and the terms were recorded in an email of 28 March 2019 that mentioned only the shares. The next day the Kotharis emailed a "break-up" treating the Rs 36.75 crore as including repayment of the Agrawals' Rs 10.29 crore loan, which the Agrawals expressly rejected in several emails. The Kotharis sued for specific performance and the Agrawals submitted to a consent decree in terms of the 28 March email. In execution, a single judge of the Bombay High Court called the decree "ambiguous," looked into the pleadings (to which the Agrawals had filed no written statement) and held the price was inclusive of the loan; the Division Bench agreed.

Decision Breakdown

The Supreme Court allowed the appeal and set aside the High Court's orders. Reaffirming Topanmal Chhotamal (1960) and Meenakshi Saxena (2018), it held that an executing court must take the decree as it stands and cannot go behind it; while it may construe a genuinely ambiguous decree by reference to the judgment and pleadings, it cannot add terms the parties never agreed. Here the consent decree mirrored the 28 March email, which spoke only of the sale of shares; the loan inclusion appeared for the first time in the Kotharis' 29 March email and was expressly refused, so there was "a clear lack of consensus." The 2017 joint venture agreement itself provided a separate mechanism for repaying a seller's loans within 15 days of a bid, confirming that the share price and the loan were distinct. The Agrawals' failure to file a written statement could attract an adverse inference but could not justify expanding the decree; "the stream cannot rise above its source."

Lesson Learnt

A court enforcing a decree can only enforce what the decree actually says; it cannot rewrite a consent decree to include terms one side proposed but the other side rejected. Parties settling a dispute should ensure every financial component, such as loans owed alongside a share sale, is spelled out explicitly in the document that becomes the decree.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case