SEPCO Electric Power Construction Corporation vs. GMR Kamalanga Energy Ltd.

Not available · 2025 INSC 1171Decided 26 Sept 2025
Not available
Chief Justice B.R. Gavai · Justice Augustine George Masih

Background

SEPCO and GMR Kamalanga Energy Ltd. (GMRKE) were parties to EPC agreements for a power project. An Arbitral Tribunal passed an award largely in SEPCO's favour, which a Single Judge of the Orissa High Court upheld under Section 34 of the Arbitration Act. On appeal under Section 37, a Division Bench of the High Court set aside both the Section 34 judgment and the arbitral award itself, holding that the Tribunal had treated the two parties unequally and had gone beyond its mandate. SEPCO then appealed to the Supreme Court.

Decision Breakdown

The Supreme Court examined whether the Division Bench had exceeded the narrow scope of interference permitted under Sections 34 and 37. It found that the Arbitral Tribunal had discriminated between the parties (allowing SEPCO's claims despite SEPCO's own failure to issue mandatory contractual notices, while rejecting GMRKE's counter-claims for the very same failure) which violated the principle of equal treatment under Section 18 of the Act and the public policy of India. The Court also agreed that the Tribunal had effectively rewritten the contract by treating a failed Unit Characteristic Test as if the Performance Guarantee Test had been validly completed, going beyond its mandate. Given these fundamental defects, the Supreme Court held that the Division Bench was right to fully set aside the award rather than sever the bad parts from the good, and dismissed SEPCO's appeal with no order as to costs.

Lesson Learnt

Courts can and will set aside an arbitral award, even though judicial interference with arbitration is meant to be minimal, where the tribunal treats the parties unequally or rewrites the contract beyond its mandate, since such defects strike at the fundamental policy and public policy of Indian law.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case