Sepco Electric Power Construction Corporation vs Power Mech Projects Ltd.

SLP(C) · 2022 INSC 981Decided 19 Sept 2022
SLP(C) No. 4511 of 2021
Indira Banerjee · Krishna Murari

Background

Sepco, a Chinese company executing coal-power project contracts in India, engaged Power Mech as a sub-contractor. A dispute went to arbitration, resulting in an award of about Rs. 142 crore in Power Mech's favour. Sepco challenged the award in the Delhi High Court under Section 34 of the Arbitration Act and separately sought a stay of the award under Section 36(2), while Power Mech sought interim security for the award amount under Section 9. The High Court eventually directed Sepco to deposit the full Rs. 142 crore (after adjusting an earlier bank guarantee and part-deposit) to secure the award, and stayed enforcement only on that deposit being made. Sepco appealed to the Supreme Court, arguing its earlier-filed stay application should have been decided first and that the deposit order was too harsh.

Decision Breakdown

The Supreme Court held there is no fixed rule that an application filed earlier in time must be decided before a later one, and that both the Section 9 (interim security) and Section 36(2) (stay) applications concerned overlapping issues that could properly be considered together. It found Sepco had not shown any cogent, prima facie ground (such as fraud, corruption, or a glaring error going to the root of the award) to justify an unconditional stay; a large award (Rs. 142 crore) genuinely existed against it, and Power Mech had a strong case for interim protection. The Court held the High Court had acted well within its wide powers under Section 9 in directing the deposit, and dismissed Sepco's appeals, while asking the High Court to dispose of the underlying challenge to the award as expeditiously as possible.

Lesson Learnt

A party challenging an arbitral award is not automatically entitled to an unconditional stay merely by filing that challenge; courts can and often will require the challenging party to secure the awarded amount (by deposit or bank guarantee) unless it shows a strong prima facie case of fraud or a fundamental flaw in the award.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case