Shakti Nath & Ors. v. Alpha Tiger Cyprus Investment No. 3 Ltd. & Ors.

Civil Appeal · 2020 INSC 203Decided 18 Feb 2020
Civil Appeal No. 1674 of 2020
Justice Uday Umesh Lalit · Justice Indu Malhotra

Background

The appellant-promoters had entered into shareholder agreements with the respondent-investors to jointly develop an IT Special Economic Zone project on leased NOIDA land, but later terminated the agreements soon after the investors brought in their contribution of Rs. 45 crore. The investors won an ICC arbitral award (by 2:1 majority) directing repayment with heavy interest and costs. The promoters' challenge to this award failed before a Single Judge and then a Division Bench of the Delhi High Court, leading to this further appeal to the Supreme Court, during which the Court had already secured deposits and an injunction on the promoters' land to protect the investors' eventual recovery.

Decision Breakdown

The Supreme Court rejected the promoters' challenge to the arbitral award. However, rather than simply enforcing the original award figures, the Court recorded and approved a negotiated commercial settlement reached by all parties during the hearing: the promoters agreed to pay a reduced lump sum of Rs. 107.5 crore in full and final settlement, funded partly through a buyer (the Bhutani Group) purchasing the underlying project company's shares and depositing the sale proceeds with the Court, and partly through the promoters raising funds themselves (for which an earlier injunction on their other property was lifted). The appeal was disposed of strictly on these consent terms, with a default clause reviving the full original award if the promoters failed to pay.

Lesson Learnt

Even after the Supreme Court upholds an arbitral award on the law, the parties remain free to negotiate a practical, court-supervised commercial settlement to actually satisfy the award, and the Court will record and enforce such a settlement (including through conditional safeguards) rather than mechanically restating the original award figures.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case