Shripati Lakhu Mane vs The Member Secretary, Maharashtra Water Supply and Sewerage Board & Ors.

Civil Appeal · 2022 INSC 368Decided 30 Mar 2022
Civil Appeal No. 556 of 2012
Hemant Gupta · V. Ramasubramanian

Background

A registered government contractor was awarded a water supply pipeline project in Maharashtra in 1986, but the work order was repeatedly put on hold, modified, and disrupted by the awarding authority, including a change in pipe specifications, a directive to switch work to a different site, and delayed payment of bills due to fund shortages. When the contractor's work slowed amid these disputes, the authority accused him of "abandoning" the contract and refused to pay several of his claims. The trial court awarded the contractor about Rs. 24.97 lakh with interest, but the Bombay High Court, on appeal by the authority, cut this down to about Rs. 7.19 lakh, chiefly by disallowing claims linked to the alleged "abandonment."

Decision Breakdown

The Supreme Court reviewed the entire correspondence timeline and found that it was the authority, not the contractor, that repeatedly disrupted performance of the contract, including keeping the work order in abeyance, changing specifications without finalizing new rates, and failing to pay bills on time. Citing Section 67 of the Indian Contract Act, the Court held that when a party neglects to give the other side reasonable facilities to perform, the other party is excused from non-performance, and this could not be labelled "abandonment." The Court also noted the authority's own conduct was inconsistent with an abandonment theory, since it later granted the contractor a further extension of time rather than terminating the contract for breach. Finding the High Court had erred in law, the Supreme Court restored the trial court's original, larger award in favour of the contractor.

Lesson Learnt

A contractor cannot be blamed for "abandoning" a contract when it is the other party's own delays, changed specifications, or non-payment that prevented performance, under contract law, a party who is denied reasonable facilities to perform is legally excused for resulting non-performance.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case