Som Datt Builders-NCC-NEC (JV) v. National Highways Authority of India & Ors.

Civil Appeal · 2025 INSC 113Decided 27 Jan 2025
Civil Appeal No. 2058 of 2012
Justice Abhay S. Oka · Justice Ujjal Bhuyan

Background

A construction joint venture was contracted by the National Highways Authority of India (NHAI) to build a highway stretch, including a wall requiring a material called "geogrid." The actual quantity of geogrid needed turned out to be far higher than originally estimated in the contract's Bill of Quantities. NHAI wanted to renegotiate the rate for the excess quantity; the contractor said the original rate should apply since there was no change in design, only an increase in quantity. A technical Dispute Review Board and then a three-member Arbitral Tribunal both sided with the contractor. A single judge of the Delhi High Court upheld the award, but a Division Bench of the same High Court later overturned it, prompting this appeal.

Decision Breakdown

The Supreme Court restored the arbitral award, holding that the Division Bench had exceeded its very limited power of review under Section 37. Courts reviewing arbitration awards cannot re-interpret contract clauses simply because they might have read a "variation" clause differently; they can only step in if the award is arbitrary, perverse, or shocks the conscience of the court. Here, three technical bodies (the Dispute Review Board, the Arbitral Tribunal, and the single judge) had all reasonably concluded that an increase in quantity without any actual design change was not a "variation" requiring renegotiated rates, since the contract itself anticipated that estimated quantities might turn out to be wrong. The Division Bench's contrary reading, based on dictionary definitions rather than the contract's own scheme, was an overreach.

Lesson Learnt

Once a technical dispute has been decided by an arbitrator or expert tribunal and upheld once in court, appellate courts have very narrow room to second-guess that interpretation, disagreeing with a "plausible" reading of a contract is not enough to overturn an arbitration award.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case