Standard Chartered Bank v. Andhra Bank Financial Services Ltd. & Ors.

Civil Appeal · Neutral citation not assigned (Civil Appeal Nos. 9540-9541 of 2010)Decided 28 Aug 2015
Civil Appeal Nos. 9540-9541 of 2010
Justice V. Gopala Gowda · Justice R. Banumathi

Background

In the 1992 Indian securities scam, Standard Chartered Bank (SCB) had paid Andhra Bank Financial Services Ltd. (ABFSL) about Rs. 48 crore for 17% NPCL bonds, but the bonds' original letter of allotment was instead diverted, through broker Hiten P. Dalal, to Canara Bank Mutual Fund (CMF), which then resold the same bonds to SCB a second time. When the scam surfaced, SCB sued ABFSL in the Special Court set up to try securities-scam cases, and later sought to add Hiten P. Dalal and CMF as defendants for conversion (wrongful dealing with SCB's property) once CBI's investigation revealed the diversion. The Special Court had dismissed the claim against these added respondents as time-barred, holding that SCB's own suit against them had not been filed within the limitation period.

Decision Breakdown

The Supreme Court examined in detail when SCB could be said to have acquired real "knowledge" (as required under Article 91(a) of the Limitation Act) that the respondents had converted its bonds, and rejected the respondents' argument that an earlier vague and evasive disclosure by broker Hiten P. Dalal in May 1992 started the limitation clock. It held that limitation began running only from 7 November 1992, by which point SCB had sufficiently concrete knowledge of the conversion, making its 1995 application to add the respondents timely. Since the Special Court's findings on the merits of the claim itself had not been separately challenged by the respondents, the Court held SCB was entitled to a decree for the principal sum (recalculated at about Rs. 50.18 crore) plus 6% annual interest from January 1996 until realisation, with the respondents held jointly and severally liable, and it set aside the dismissal on the limitation point while allowing the appeals.

Lesson Learnt

In fraud or scam-related claims, the clock for limitation runs from when a party actually acquires clear, non-vague knowledge of the wrongdoing against them, not from an earlier ambiguous hint or rumour, so victims of fraud are not unfairly shut out of court merely because suspicious circumstances existed earlier.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case