State Bank of India vs. K R Anand

Original Miscellaneous Petition (Commercial) · 2026:DHC:7793Decided 15 Sept 2026New Delhi Bench
O.M.P. (COMM) 69/2024CNR: DLHC010035702024
Justice Avneesh Jhingan

Background

SBI had engaged a contractor to build 76 officer flats in Noida; the work was delayed well beyond the contract period and completed only after three time extensions. After completion, the contractor claimed several kinds of compensation through arbitration for the delay (allegedly caused by SBI), including overhead costs, price adjustment for inflation, and interest on delayed payments. The arbitrator awarded the contractor about Rs. 1.43 crore, and SBI challenged four specific parts of that award in court.

Decision Breakdown

The Court set aside the arbitrator's award of "overhead expenses" for delay, because the contractor had never actually proven its real financial loss: the arbitrator had simply applied a standard formula (the "Emden formula") without the evidence Indian law requires to justify such damages. It also struck down the price-adjustment award for the contract's third time extension, since the record showed that extension was expressly granted without any price benefit, and the arbitrator's reasoning for awarding it anyway did not hold up. However, the Court upheld the parts of the award granting interest for SBI's delay in paying running bills/final bill and in returning the contractor's security deposit, finding the arbitrator's view on those points reasonable and unchallengeable.

Lesson Learnt

Even in arbitration, a party claiming financial losses (like "overhead costs" from project delay) must actually prove those losses with evidence: a mathematical formula alone is not a substitute for proof, and courts will strike down arbitration awards that skip this step.

Arbitration & Commercial LawSupreme Court of India

Shreeram Builders v. Upendra Kantilal Thanawala & Ors.

The Supreme Court upheld setting aside the award, though for more precise reasons, holding that stamp duty classification alone wasn't decisive, but the arbitrators had exceeded their authority by effectively rewriting the contract: the price was never fixed, full consideration was never paid by deadline, and the arbitrators invented an unexplained price multiplier and damages the contract never provided for. Invoking its Article 142 power to do complete justice, the Court ordered the owners to refund all amounts received from the builder with 9% interest, since they never returned the payments after terminating the deal.

Decided 29 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S S.R. Ashok & Associates vs. Delhi Development Authority & Anr. and connected matters

The Court rejected the time-bar argument since the arbitration invocation was a single continuing one and DDA had consented to delays while participating throughout. It found no error apparent on the face of either award, upholding both and making them enforceable court decrees.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Axis Finance Ltd vs. Mr Nikhil A V & Ors.

The Court granted leave and liberty to withdraw and dismissed the petition without ruling on the underlying dispute.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

MMTC Limited vs. Aust Grain Exports Pty Ltd

The Court rejected MMTC's procedural and compensation arguments but found one real flaw: the tribunal had expressly rejected the exporter's claim for interest on the refunded guarantee (since the contract barred it), yet then awarded that very interest anyway, a direct, unexplained contradiction. The Court struck out only that contradictory portion as severable, leaving the rest of the award intact.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Chief Electoral Officer & Anr. vs. M/S Mahlakshmi Light House

The government argued the arbitrator ignored an internal inquiry suggesting inflated bills. The Court held returning officers who checked goods at the time gave more reliable evidence than a later inquiry report, and this specific objection was never raised before the single judge, so couldn't be raised for the first time on appeal. The appeal was dismissed.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Utracon Corporation Pte Ltd vs. Ucon PT Structural System Private Limited (formerly Utracon Structural Systems Private Limited) & Ors.

The defendant applied to refer the whole suit to arbitration, arguing the real dispute was about contractual rights to use the marks between identified parties (not a trademark registration or grant dispute, which can't be arbitrated), flowing from a single composite transaction. The Court agreed: the arbitration clause's existence was undisputed, the dispute was essentially contractual, and since the plaintiff itself had pleaded that the other defendants formed a "single economic unit" with the main defendant and derived their rights "through" it, their claims couldn't be separated out either; any question of whether they were bound by the arbitration clause was for the arbitrator to decide. The Court referred the whole suit to arbitration and disposed of it, expressly offering no opinion on the merits.

Decided 28 Oct 2026Read case