Steel Authority of India vs. Norvic Shipping North America Inc

Original Miscellaneous Petition (Commercial) · 2026:DHC:8140Decided 22 Sept 2026New Delhi Bench
O.M.P. (COMM) 260/2023CNR: DLHC010277772023
Justice Avneesh Jhingan

Background

SAIL had contracted with the Canada-incorporated shipping company Norvic to transport 1.6 million metric tons of limestone from the UAE to India over multiple voyages. Disputes arose over how long each ship was allowed to sit before being charged "demurrage" (a penalty for delay) at various Indian ports, especially given delays from a cyclone and, later, the Covid-19 pandemic and lockdown. An arbitral tribunal awarded Norvic freight, demurrage, and interest across seven vessels, and SAIL challenged that award in court.

Decision Breakdown

The Court dismissed SAIL's challenge across all seven vessels. It held this was an "international commercial arbitration" (since Norvic is a foreign company) seated in Delhi, meaning the more limited grounds for challenging domestic awards (like "patent illegality") don't apply: the award can only be set aside for narrower reasons, such as being genuinely bereft of reasoning or contrary to fundamental policy. On the facts, the Court found the tribunal had properly considered whether notices of a ship's arrival readiness were valid, whether equipment breakdowns should pause the delay-clock, and crucially, whether Covid-19 restrictions actually prevented cargo unloading, noting that government orders at the time expressly classified port cargo operations as "essential services" that were required to continue, undercutting SAIL's claim that the pandemic excused its delays. It also upheld the interest rate awarded (LIBOR + 3%, capped at 12% per annum) as clear and not open-ended.

Lesson Learnt

In cross-border commercial disputes, once an arbitration is classified as "international commercial arbitration," Indian courts apply a much narrower standard when reviewing the award: they will not re-examine the tribunal's factual findings or substitute their own view, even on matters like whether Covid-19 lockdown orders genuinely prevented contract performance, so long as the tribunal's reasoning is intelligible and grounded in the evidence before it.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case