Supertech Ltd and Others vs. Indiabulls Housing Finance Ltd. and Anr.

Original Miscellaneous Petition (Interim, Commercial) · 2026:DHC:8169Decided 22 Sept 2026New Delhi Bench
O.M.P.(I) (COMM.) 89/2022CNR: DLHC010108182022
Justice Om Prakash Shukla

Background

Two of three petitioners (Supertech Ltd and another company) had sought interim protective measures against a housing finance lender under Section 9 of the Arbitration and Conciliation Act. At the hearing, counsel for the first two petitioners sought leave to withdraw the petition, while no one appeared on behalf of the third petitioner.

Decision Breakdown

The Court allowed the withdrawal as to Petitioners 1 and 2, and separately dismissed the petition for want of prosecution as to Petitioner 3 since no one appeared for it. The Court clarified that all petitioners remain free to pursue whatever legal remedies are available to them in law.

Lesson Learnt

A party can withdraw its own interim arbitration petition at any stage, but a co-petitioner who fails to appear risks having its own claim dismissed for non-prosecution rather than simply being carried along with the withdrawal.

Arbitration & Commercial LawSupreme Court of India

Shreeram Builders v. Upendra Kantilal Thanawala & Ors.

The Supreme Court upheld setting aside the award, though for more precise reasons, holding that stamp duty classification alone wasn't decisive, but the arbitrators had exceeded their authority by effectively rewriting the contract: the price was never fixed, full consideration was never paid by deadline, and the arbitrators invented an unexplained price multiplier and damages the contract never provided for. Invoking its Article 142 power to do complete justice, the Court ordered the owners to refund all amounts received from the builder with 9% interest, since they never returned the payments after terminating the deal.

Decided 29 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S S.R. Ashok & Associates vs. Delhi Development Authority & Anr. and connected matters

The Court rejected the time-bar argument since the arbitration invocation was a single continuing one and DDA had consented to delays while participating throughout. It found no error apparent on the face of either award, upholding both and making them enforceable court decrees.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Axis Finance Ltd vs. Mr Nikhil A V & Ors.

The Court granted leave and liberty to withdraw and dismissed the petition without ruling on the underlying dispute.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

MMTC Limited vs. Aust Grain Exports Pty Ltd

The Court rejected MMTC's procedural and compensation arguments but found one real flaw: the tribunal had expressly rejected the exporter's claim for interest on the refunded guarantee (since the contract barred it), yet then awarded that very interest anyway, a direct, unexplained contradiction. The Court struck out only that contradictory portion as severable, leaving the rest of the award intact.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Chief Electoral Officer & Anr. vs. M/S Mahlakshmi Light House

The government argued the arbitrator ignored an internal inquiry suggesting inflated bills. The Court held returning officers who checked goods at the time gave more reliable evidence than a later inquiry report, and this specific objection was never raised before the single judge, so couldn't be raised for the first time on appeal. The appeal was dismissed.

Decided 28 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

Utracon Corporation Pte Ltd vs. Ucon PT Structural System Private Limited (formerly Utracon Structural Systems Private Limited) & Ors.

The defendant applied to refer the whole suit to arbitration, arguing the real dispute was about contractual rights to use the marks between identified parties (not a trademark registration or grant dispute, which can't be arbitrated), flowing from a single composite transaction. The Court agreed: the arbitration clause's existence was undisputed, the dispute was essentially contractual, and since the plaintiff itself had pleaded that the other defendants formed a "single economic unit" with the main defendant and derived their rights "through" it, their claims couldn't be separated out either; any question of whether they were bound by the arbitration clause was for the arbitrator to decide. The Court referred the whole suit to arbitration and disposed of it, expressly offering no opinion on the merits.

Decided 28 Oct 2026Read case