Suresh Shah v. Hipad Technology India Private Limited

Arbitration Petition (Civil) · 2020 INSC 711Decided 18 Dec 2020
Arbitration Petition (Civil) No. 08 of 2020
Chief Justice S.A. Bobde · Justice A.S. Bopanna · Justice V. Ramasubramanian

Background

Suresh Shah, a Kenyan national holding a long-term lease over a commercial property in NOIDA, had sub-leased it to Hipad Technology under a sub-lease deed containing an arbitration clause. A dispute arose between the parties, and Shah sought to invoke arbitration, nominating a retired judge as sole arbitrator, but Hipad did not respond. Since the sub-lease agreement named the Delhi High Court as the appointing authority for the arbitrator, but Shah's foreign nationality made this an "International Commercial Arbitration," he approached the Supreme Court directly under Section 11(6) of the Arbitration and Conciliation Act, 1996 for the appointment.

Decision Breakdown

Before appointing the arbitrator, the Court addressed a broader legal question: whether landlord-tenant disputes can be resolved through arbitration at all. It held that tenancy disputes governed by special rent-control statutes (which give tenants statutory protection against eviction) are not arbitrable, since only courts specified under those statutes have jurisdiction. However, where a lease is governed simply by the general Transfer of Property Act, 1882, with no special statutory protection, the dispute is arbitrable, following the Court's recent view in Vidya Drolia and departing from the narrower view in Himangni Enterprises. Since this lease was a simple TP Act lease with an arbitration clause, the Court allowed the petition and appointed Justice (Retired) Mukul Mudgal as the sole arbitrator.

Lesson Learnt

Not every landlord-tenant dispute can be arbitrated: if your lease is covered by a special rent-control law that protects tenants, only the courts named in that law can resolve the dispute; but an ordinary commercial lease without such special protection can be sent to arbitration if the parties have agreed to it.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case