The Project Director, National Highways No. 45E and 220, National Highways Authority of India v. M. Hakeem

Civil Appeal · 2021 INSC 344Decided 20 Jul 2021
Civil Appeal No. 2797 of 2021
Justice Rohinton Fali Nariman · Justice B.R. Gavai

Background

Landowners whose land was acquired for national highway projects were dissatisfied with the compensation fixed by the competent authority and referred their disputes to arbitration under the National Highways Act, 1956. When they challenged the arbitral awards under Section 34 of the Arbitration Act seeking higher compensation, some High Courts (and in one instance a civil court) went further than simply setting aside the awards: they actually enhanced the compensation themselves. The National Highways Authority of India (NHAI) challenged this practice, arguing that courts have no power to modify an arbitral award under Section 34; they can only set it aside.

Decision Breakdown

The Supreme Court held that Section 34 of the Arbitration Act only allows a court to set aside an arbitral award on limited grounds: it does not give the court power to modify, vary, or enhance the award itself, since the provision is modelled on the UNCITRAL Model Law, which deliberately omits any power of modification (unlike the earlier Arbitration Act, 1940). Allowing courts to "modify" awards under the guise of "setting aside" would amount to the court exercising appellate powers over an arbitrator's decision, which defeats the object of minimal judicial interference in arbitration. However, despite declaring this point of law in NHAI's favour, the Court declined to actually disturb the specific enhanced-compensation orders in these particular appeals, noting that similarly placed landowners had already received the higher amounts from NHAI in other cases, the awards were 7-10 years old, and it would be unfair at this late stage to send the matter back for a fresh arbitration.

Lesson Learnt

If you lose an arbitration case and go to court to challenge the award, the court can only cancel (set aside) a flawed award: it cannot rewrite the award or award you a different amount itself; a flawed award, once set aside, generally has to go back to fresh arbitration, not be substituted by the court's own figure.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case