The State of Gujarat Through Chief Secretary v. Amber Builders

Civil Appeal · 2020 INSC 16Decided 8 Jan 2020
Civil Appeal No. 8307 of 2019
Justice Deepak Gupta · Justice Aniruddha Bose

Background

A contractor had built and later repaired a stretch of national highway for the Gujarat government under a works contract containing an arbitration clause. Years after the work was completed and the security deposit released, the State sent a notice demanding over Rs.1.09 crore, alleging the repair work was defective, and threatened to recover this by withholding payments owed to the contractor under separate, unrelated contracts. The contractor challenged this in the Gujarat High Court, which ruled in its favour and barred the State from such recovery; the State then appealed to the Supreme Court.

Decision Breakdown

The core question was whether the special tribunal created under the Gujarat Public Works Contracts Disputes Arbitration Tribunal Act, 1992 had the power to grant interim relief (such as injunctions) the way a court could under Section 17 of the Arbitration and Conciliation Act, 1996. The Supreme Court held that the Gujarat Act's tribunal does have this power, because Section 17 of the general arbitration law supplements rather than conflicts with the state tribunal's existing powers. Since this dispute was squarely a "works contract" dispute covered by the Gujarat Act, the High Court should never have entertained the writ petition at all: the contractor's correct remedy was to approach the Tribunal. The Court set aside the High Court's judgment on this jurisdictional ground, without commenting on who was actually right about the disputed repair work, and gave the contractor two months to approach the Tribunal, directing that it not be denied a hearing on grounds of delay.

Lesson Learnt

When a special law sets up a dedicated tribunal for a specific category of disputes (such as government works contracts), parties must go to that tribunal rather than file a writ petition in the High Court, and such tribunals generally can exercise the same interim-relief powers as a court under the general arbitration law.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case