The State of Jharkhand & Ors. v. M/S HSS Integrated SDN & Anr.

Special Leave Petition (Civil) · 2019 INSC 1169Decided 18 Oct 2019
Special Leave Petition (Civil) No. 13117 of 2019
Justice Arun Mishra · Justice M.R. Shah

Background

The State of Jharkhand had engaged a consultancy consortium to supervise construction of the Ranchi Ring Road. After citing performance deficiencies, the State suspended payments and eventually terminated the contract. The consultants challenged the termination as illegal and claimed unpaid dues and losses through arbitration; the State filed a counter-claim for the consultants' alleged poor performance. The Arbitral Tribunal found the termination illegal and awarded the consultants about Rs. 2.1 crore (roughly 41% of their claim) while rejecting the State's counter-claim, and this award was upheld by both a trial court and the Jharkhand High Court.

Decision Breakdown

The Supreme Court dismissed the State's further appeal, reaffirming the well-settled, narrow scope of judicial review over arbitral awards: courts examining an award under Sections 34 and 37 of the Arbitration Act cannot re-assess evidence like an appellate court, and can interfere only if the arbitrator's findings are perverse, contrary to the evidence, or against public policy. Since the Tribunal had given detailed, evidence-based reasons (running to twenty paragraphs) for finding the termination illegal, and had carefully allowed some claims, partly allowed others, and disallowed the rest with a reasoned breakdown, the Court held these were legitimate findings of fact that three forums (Tribunal, trial court, High Court) had already concurrently upheld, leaving no basis for further interference.

Lesson Learnt

Once an arbitration award is based on a reasoned, evidence-backed view of the contract, courts will not re-open or second-guess that view merely because a party disagrees with it: an arbitrator's factual findings are treated as largely final unless they are perverse or violate public policy.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case