The State of Madhya Pradesh vs M/s SEW Infrastructure Limited (Construction) Ltd. & Ors.
Background
A contractor was engaged in 1993 to build a masonry dam for the Madhya Pradesh government, sourcing sand from a specified quarry. When that quarry ran out of sand, the department permitted the contractor to switch to a more distant quarry in 2002, but stated this was subject to a contract clause barring extra payment for the changed "lead" (transport distance) unless authorized in writing by the Superintending Engineer. The contractor later claimed roughly Rs. 5.5 crore in cost escalation for the extra transport distance; the State refused, and the dispute went to arbitration where the contractor's claim was allowed and upheld through a revision in the High Court, prompting the State's appeal here.
Decision Breakdown
The Supreme Court held that the contract's escalation clause (3.11(A)) permitted extra payment where circumstances were beyond the contractor's control AND the Superintending Engineer had granted a written order, both conditions were met here, since an inspection report confirmed the original quarry was depleted and the Superintending Engineer's letter granted permission for the alternate site. The Court held that the Executive Engineer's later attempt to impose a "no extra payment" condition exceeded his authority once the Superintending Engineer's conditions were satisfied, since contractual rights cannot be curtailed by an officer's discretion outside the contract's terms. The Court also rejected the State's res judicata argument, since an earlier, separate arbitration award concerned a different, rejected request for an alternate quarry, not this one. The appeal was dismissed and the arbitral award in the contractor's favour was upheld.
Lesson Learnt
In government contracts, once the specific conditions of a clause allowing extra payment (such as written authorization from the designated officer) are satisfied, no subordinate official can unilaterally impose additional restrictions to defeat that contractual right: the terms of the contract, not administrative discretion, govern the outcome.