The State of Madhya Pradesh vs M/s SEW Infrastructure Limited (Construction) Ltd. & Ors.

Civil Appeal · 2022 INSC 1217Decided 18 Nov 2022
Civil Appeal No. 8571 of 2022
A.S. Bopanna · Pamidighantam Sri Narasimha

Background

A contractor was engaged in 1993 to build a masonry dam for the Madhya Pradesh government, sourcing sand from a specified quarry. When that quarry ran out of sand, the department permitted the contractor to switch to a more distant quarry in 2002, but stated this was subject to a contract clause barring extra payment for the changed "lead" (transport distance) unless authorized in writing by the Superintending Engineer. The contractor later claimed roughly Rs. 5.5 crore in cost escalation for the extra transport distance; the State refused, and the dispute went to arbitration where the contractor's claim was allowed and upheld through a revision in the High Court, prompting the State's appeal here.

Decision Breakdown

The Supreme Court held that the contract's escalation clause (3.11(A)) permitted extra payment where circumstances were beyond the contractor's control AND the Superintending Engineer had granted a written order, both conditions were met here, since an inspection report confirmed the original quarry was depleted and the Superintending Engineer's letter granted permission for the alternate site. The Court held that the Executive Engineer's later attempt to impose a "no extra payment" condition exceeded his authority once the Superintending Engineer's conditions were satisfied, since contractual rights cannot be curtailed by an officer's discretion outside the contract's terms. The Court also rejected the State's res judicata argument, since an earlier, separate arbitration award concerned a different, rejected request for an alternate quarry, not this one. The appeal was dismissed and the arbitral award in the contractor's favour was upheld.

Lesson Learnt

In government contracts, once the specific conditions of a clause allowing extra payment (such as written authorization from the designated officer) are satisfied, no subordinate official can unilaterally impose additional restrictions to defeat that contractual right: the terms of the contract, not administrative discretion, govern the outcome.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case