The State of Rajasthan and Anr. vs Ultratech Cement Ltd.

Civil Appeal · 2022 INSC 871Decided 26 Aug 2022
Civil Appeal No. 5841 of 2022
N.V. Ramana · Hima Kohli · C.T. Ravikumar

Background

Ultratech Cement wanted to set up a large cement plant in Rajasthan and needed government land, including some plots officially recorded in revenue records as "Johad" (a pond/water body), to be allotted to it for a mining lease. Two separate site inspections by the local Tehsildar, and repeated recommendations by the District Collector, found that no actual water body existed on the disputed land and recommended reclassifying it. The State Government nonetheless refused to allot the land, citing the "Johad" classification and an earlier High Court ruling restricting alienation of water-body land, leading the company to approach the High Court, which ultimately ruled in the company's favour and directed processing of the allotment.

Decision Breakdown

The Supreme Court examined the two Tehsildar inspection reports, the District Collector's repeated recommendations, and a Gram Panchayat resolution, all consistently confirming no pond actually existed on the land, and held that the State Government had never disputed or challenged these findings through proper channels or evidence. It rejected the State's reliance on general environmental-law precedents (like Vellore Citizens' Welfare Forum and the Precautionary Principle), holding that those principles apply where the environmental impact is uncertain, not here where site inspections definitively showed no water body existed. The Court also held that an earlier High Court ruling (Abdul Rahman) restricting alienation of pond land had been misread by the State, since it did not bar correction of the revenue record where no pond in fact existed. The appeal by the State was dismissed and the High Court's direction to process the land allotment, subject to the company's undertakings for environmental compensatory measures, was upheld.

Lesson Learnt

A land parcel's official revenue classification (such as "pond" or "Johad") is not conclusive if repeated, unchallenged, on-ground inspection reports establish that no such feature actually exists: authorities cannot rely on outdated or incorrect land records to block a lawful claim when their own officers' findings say otherwise.

Environmental LawDelhi High Court

Pradeep Kumar Gupta vs. Delhi Development Authority

The Division Bench dismissed the appeal. It held that unauthorised parking itself is a misuse of the regulated floodplain, regardless of whether any dumping occurred. The Rs 5,000 compensation under the NGT's para 94(vi)(d) relates to throwing pooja or other material into the river, not to parking, so it did not apply. The lack of parking space due to renovation did not justify parking in a prohibited, environmentally sensitive area. The appellant had been given a personal hearing on its representation before the rejection order, so the no-hearing complaint also failed.

Decided 1 Oct 2026Read case
Environmental LawDelhi High Court

M/s Carnival Greens vs. Delhi Pollution Control Committee & Ors.

This was a very short, procedural order. The DPCC's counsel confirmed to the Court, on instructions, that only a show-cause notice had been issued so far and that the petitioner would be given a personal hearing before the DPCC decided anything. On the strength of this assurance being placed on record, the Court disposed of the writ petition without deciding any of the substantive issues raised (about infrastructure gaps or a provisional consent), since the DPCC had committed to hearing the petitioner out first.

Decided 18 Sept 2026Read case
Environmental LawDelhi High Court

M/S Ambria Cafe vs. Delhi Pollution Control Committee (DPCC) & Ors.

Notice was issued in the petition, and counsel for DPCC accepted notice on its behalf. DPCC's counsel clarified, on instructions, that only a show cause notice (not a final closure/compensation order) had been issued, and assured the Court that the petitioner would be given a personal hearing before any final decision was taken. Taking this statement on record, the Court disposed of the writ petition without deciding the underlying merits.

Decided 18 Sept 2026Read case
Environmental LawSupreme Court of India

M/S Punahchakran Private Limited v. Indotech Waste Solution

The Supreme Court held that the CPCB's 2016 revised guidelines for bio-medical waste facilities are mandatory and binding even though never published in the Official Gazette, since publication on the CPCB's official website was a reasonably sufficient mode of notice for such technical guidelines. However, the Court found that Punahchakran's relaxation from the standard 1-acre land requirement was validly granted: its facility was in a rural area (a permitted ground for relaxation) and the CPCB had been properly consulted and had imposed additional safeguard conditions. The Court also clarified that land allotment is not a strict legal precondition for starting the environmental-clearance application process, and that the original 2021 Terms of Reference remained valid (having a four-year validity period) even though the first EC based on it was earlier quashed, so the second EC could validly rely on that same original study. Concluding that the NGT had erred in quashing the second EC and CTE, the Supreme Court set aside the NGT's judgment and restored Punahchakran's approvals.

Decided 7 Sept 2026Read case
Environmental LawSupreme Court of India

Fisherman Care v. Government of India, Department of Animal Husbandry, Dairying and Fisheries

The Supreme Court held there is no real conflict between the Centre's power to regulate fishing in the EEZ (under Entry 57 of List I, exercised via the new EEZ Rules, 2025) and the State's power to regulate fishing within its territorial waters (under Entry 21 of List II, via the Tamil Nadu Marine Fishing Regulation Rules): these are two co-equal, autonomous legislative spheres that must operate together through "cooperative federalism." Following the Expert Committee's recommendations (that an outright ban on purse seine nets isn't justified but effective regulation is needed), the Union had already notified the EEZ Rules, 2025 creating an "Access Pass" system for vessels to transit through State waters into the EEZ. However, the Court found the on-ground implementation deeply flawed: of 257 access-pass applications, 226 were stuck pending verification by Tamil Nadu authorities, with only 6 passes actually issued, the lowest among all coastal States, which the Court said effectively amounted to an unwritten, unlawful ban. The Court directed Tamil Nadu to process applications efficiently and to frame rules designating a specific transit channel through its territorial waters for vessels headed to the EEZ, and disposed of the application on this basis.

Decided 2 Sept 2026Read case
Environmental LawSupreme Court of India

In Re: 2 Million Lives at Risk, Contamination in Jojari River, Rajasthan

Reviewing the SIT's report and the State's compliance report, the Court found continuing systemic failures, including that the State's report was silent on any action taken against responsible Rajasthan State Pollution Control Board officers, and issued a fresh set of detailed directions. These included: a scientific determination and demarcation of the High Flood Line and ecological buffer for the river system before any further industrial development (specifically flagging the proposed RIICO Industrial Area, Kakani, and the Ambey Valley Industrial Park as built too close to the river); an inquiry by the Chief Secretary into irregularities in land-use conversion and plot allotments at Ambey Valley; a comprehensive groundwater management strategy with a ban on new water-intensive industries in over-exploited "dark zones"; expedited transfer of identified lands to the Forest Department for ecological restoration; and a survey-and-removal drive against encroachments and illegal mining on riverbeds and floodplains. The Court also directed that action taken against RSPCB officers be reported within three days and listed the matter for further hearing on 22 September 2026, while noting that industrial pollution issues in Jaipur would be taken up separately once the present remedial framework is substantially implemented.

Decided 7 Aug 2026Read case