Union of India and Others v. U.P. State Bridge Corporation Ltd.
Background
A contractor and the Railways disagreed over construction work for a railway bridge across the Ganga near Patna. Their agreement provided for arbitration by Railway officers, but the tribunal appointed in 2007 made little progress for four years because of transfers, retirements and adjournments. It also missed the High Court's final three-month deadline, prompting that court to replace it with an independent sole arbitrator.
Decision Breakdown
The Supreme Court dismissed the Union's appeal with costs and upheld the independent appointment. Ordinarily a replacement arbitrator should be chosen through the agreed procedure, but the Court held that the repeated failure of this government-appointed tribunal justified departing from it. Returning appointment power to the same authority would leave the contractor exposed to the delay already suffered. The decision concerned how the dispute would be heard, rather than deciding the contractor's underlying claims.
Lesson Learnt
Under the arbitration framework applied in this 2014 judgment, a contractor facing a persistently non-functioning government-appointed tribunal could seek court intervention. Departure from the agreed appointment procedure required the particular failures established here, rather than merely a preference for another arbitrator.