Union of India vs. NCC Limited
Background
NCC Limited had constructed married-accommodation dwelling units for Army officers under a 2010 contract with the Union of India, but the project was delayed by 76 months (against a stipulated 24 months). An arbitral award in 2019 allowed 10 of NCC's 15 claims, awarding roughly Rs. 12.14 crore plus interest and directing release of a bank guarantee, while rejecting all of UOI's counter-claims. UOI challenged the award, while NCC sought to enforce it.
Decision Breakdown
The Court rejected most of UOI's challenges, including claims of denial of natural justice, arbitrator bias, and improper extension of the arbitrator's mandate, finding the arbitrator had given the government side full and fair opportunity to be heard. However, the Court found that two specific claims (Claim Nos. 7 and 9, awarding price escalation and prolongation costs) were patently illegal, because Clause 13(B) of the contract's General Conditions expressly barred any compensation claim for periods already covered by a granted Extension of Time (EOT) under Clause 13(A), and the Supreme Court's ruling in Ramnath International Construction confirmed that such a bar is enforceable. Since the arbitrator ignored this binding contractual bar, those two claims (and the associated interest) were severed and set aside, while the rest of the award was upheld.
Lesson Learnt
Even though courts generally cannot second-guess an arbitrator's factual findings, an arbitral award that awards compensation squarely prohibited by an express contract clause (like a "no compensation for EOT-covered delay" clause) can be set aside as "patently illegal": contractors should check such bars before claiming delay-related compensation in arbitration.