WAPCOS Ltd. v. Salma Dam Joint Venture & Anr.

Civil Appeal · 2019 INSC 1249Decided 14 Nov 2019
Civil Appeal arising out of SLP (Civil) No. 7979 of 2019
Justice A.M. Khanwilkar · Justice Dinesh Maheshwari

Background

WAPCOS Ltd., a public sector undertaking, contracted Salma Dam Joint Venture (SDJV), a consortium of two companies, to build the Salma Dam project in Afghanistan. After the project cost was revised upward several times, the parties signed a formal Amendment of Agreement (AoA) in 2015 under which SDJV agreed that all its pending and future claims "stood buried" and that there would be no arbitration over them. Despite this, one of SDJV's constituent partners later tried to unilaterally invoke arbitration and get an arbitrator appointed, even though its authority to act for the joint venture had meanwhile been revoked by the other partner; the Delhi High Court nonetheless allowed the arbitration petition and appointed a sole arbitrator, prompting WAPCOS and the other partner to appeal to the Supreme Court.

Decision Breakdown

The Supreme Court held that the 2015 Amendment of Agreement had the clear effect of extinguishing the arbitration clause in the original contract: its express terms stated that pending claims stood buried and there would be no arbitration for settling claims, and SDJV had never disputed executing the AoA or claimed it was signed under duress. The Court found the Delhi High Court had rested its contrary view on factual errors (including a wrong date for the AoA) and had wrongly treated the Technical Committee's consideration of post-AoA appeals as reviving the arbitration remedy. Since there was no subsisting arbitration agreement on the date the Section 11(6) petition was filed, that petition was not maintainable at all. The Court set aside the High Court's order, dismissed the arbitration petition, but left open other legal remedies the parties might separately pursue.

Lesson Learnt

When contracting parties execute a written settlement or amendment agreement expressly giving up future claims and ruling out arbitration, that agreement overrides the arbitration clause in the original contract: a party cannot later resurrect arbitration over claims it already agreed to abandon.

Arbitration & Commercial LawSupreme Court of India

Modern Asset v. KNK Constructions Private Limited

The Supreme Court held that an arbitration clause survives termination of the underlying contract (the "doctrine of separability") and that, at the Section 11 reference stage, courts only check for the prima facie existence of an arbitration agreement: deeper questions about the effect of the resolution plan are for the arbitrator. It confirmed that while the IBC's "clean slate" principle extinguishes creditors' claims against the insolvent company once a resolution plan is approved, it does not extinguish the claims the company itself (through its SRA) may have against its own debtors, since the Resolution Professional had not raised a counter-claim on KNK's behalf during the insolvency process. However, noting the inequity of letting KNK recover fresh dues on the same contract while Modern Asset's own claim had been wiped out to 0.72 %, and following its own recent precedent in Ujaas Energy, the Court modified the High Court's order: Modern Asset may raise its extinguished claim in the arbitration solely as a set-off against any amount it is found to owe KNK, but cannot use it to claim any fresh recovery.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

S And P Infrastructure Developers (Pvt) Ltd vs. National Highways Authority of India

The Court held that the Joint Registrar's order overlooked an earlier ruling of this Court (M/s URC Construction (P) Ltd. v. Airports Authority of India) establishing that an instrument must be stamped at or before execution, with any delay attracting penalty, not just a top-up payment. Since the Joint Registrar's order was not in line with the Indian Stamp Act, 1899, the Court set it aside. The decree holder's counsel then sought to withdraw the petition with liberty to refile once the stamp duty issue was properly resolved, which the Court granted.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawSupreme Court of India

Shubham Equipment Private Limited & Anr. v. Rothwell Water Company Limited & Ors.

The Supreme Court held that the Licence Agreement, the JVA, and the MoU each covered different subject matter (technology licensing, the joint venture company, and logistics services respectively), so the JVA and MoU's own arbitration clauses, providing for arbitration in Mumbai under Indian law, governed the disputes arising under them, not the Licence Agreement's Korea clause. Both agreements also contained "entire agreement" clauses showing they were meant to stand independently. The Court restricted itself to the limited inquiry required at the reference stage under Section 11(6-A), whether an arbitration agreement prima facie exists, and left deeper questions, including whether a non-signatory subsidiary (RBIPL) could be bound, to the arbitrator. It allowed the petitions and appointed a former Chief Justice of the Bombay High Court as the sole arbitrator.

Decided 8 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt Ltd vs. Connect and Heal Primary Care Pvt. Ltd.

Since the dispute was resolved, the petitioner's counsel sought leave to withdraw the petition rather than continue with it. The Court granted leave and dismissed the petition as withdrawn, along with any pending applications.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S Redcliffe Lifetech Pvt. Ltd. vs. Lifespan Wellness Private Limited

The Court reiterated that at the stage of appointing an arbitrator under Section 11, it need only check whether an arbitration agreement exists on its face, not decide the merits of the dispute. Finding the arbitration clause undisputed, the Court appointed a named advocate as sole arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC), leaving all other objections (including arbitrability and jurisdiction) to be decided by the arbitrator.

Decided 7 Oct 2026Read case
Arbitration & Commercial LawDelhi High Court

M/S. Keshari Multi Functional Complex Pvt Ltd vs. Rail Land Development Authority

Because the awarded amount was already deposited pursuant to the earlier stay order, the Court held nothing further survived for consideration in the present enforcement petition. It disposed of the petition, giving the decree holder liberty to refile later after paying the proper stamp duty (and any penalty) under the Indian Stamp Act, 1899.

Decided 7 Oct 2026Read case