Background

Following the bifurcation of Andhra Pradesh, a dispute arose over allocating employees of the erstwhile combined State Power Utilities between the successor Andhra Pradesh and Telangana power companies. The Supreme Court had earlier accepted a "One Man Committee" report (by Justice D.M. Dharmadhikari) and, by judgment dated 7 December 2020, directed both states' power utilities to implement and absorb all employees on the Committee's final list. 84 petitioners, employees who had already been relieved by the Andhra Pradesh Power Utilities on the strength of this list, alleged that the Telangana Power Utilities (TS Genco, TS Transco, TSSPDCL and TSNPDCL) then issued office orders in December 2020 that arbitrarily left them out of absorption, in defiance of the Court's ruling, leaving them without a job or salary.

Decision Breakdown

The Supreme Court held that once the One Man Committee's Final Report and List had been accepted and made binding by its own earlier order, any deviation from it by the Telangana Power Utilities amounted to willful disobedience. It rejected the Telangana Power Utilities' attempt to re-raise "reciprocity" and "financial neutrality" objections that had already been considered and dismissed in the Court's December 2020 order, holding there must be finality to litigation. The Court found the Telangana Power Utilities guilty of civil contempt for deliberately disobeying its judgment dated 7 December 2020. However, before deciding the actual punishment, it gave the contemnors one final opportunity: two weeks to absorb all 84 petitioners as per the approved list and to pay them salary and service benefits from the date they were relieved by the Andhra Pradesh Power Utilities, with the question of sentence to be taken up on 31 October 2022 depending on compliance.

Lesson Learnt

A government body or public utility that has lost a legal battle before the Supreme Court cannot evade compliance by repeatedly re-raising the same objections through fresh administrative orders, doing so exposes it (and its officers) to a finding of contempt of court, and the Court can hold a party guilty of contempt while still giving a final, time-bound chance to comply before imposing punishment.

Contempt of CourtDelhi High Court

Mansi Brar vs. Mohit Singh

The Court found that the subject properties had already been sold before the status quo order was passed. The respondent did not disclose this in his reply and instead relied on other grounds, and the exact position emerged only after the Court directed him to file an affidavit. The Court held that the earlier order was passed on the basis of this non-disclosure, and that he had also wilfully breached his undertaking. He was held guilty of civil contempt under Section 2(b) of the Contempt of Courts Act, 1971. The text of the judgment supplied does not show a sentence or penalty.

Decided 1 Oct 2026Read case
Contempt of CourtDelhi High Court

Dr. Naresh Kumar vs. Shri Ajay Kumar Bhalla & Ors.

The Court found the respondents had in fact complied with the specific direction in the earlier order: the petitioner had been promoted to CMO (OG) as ordered, and had even been further promoted to CMO (SG) since then. Since the scope of contempt proceedings is confined to the exact directions given in the order allegedly violated, and the order never addressed promotion to DIG, the Court held the petitioner could not use contempt proceedings to expand relief to a promotion issue never covered by the original order, and dismissed the petition.

Decided 24 Sept 2026Read case
Contempt of CourtDelhi High Court

Bharat Singh Rawat vs. Dr. Poonam Singh Rawat

Relying on Supreme Court precedent (Midnapore Peoples' Coop. Bank Ltd. v. Chunilal Nanda), the Division Bench held that an appeal under Section 19 of the Contempt of Courts Act is maintainable only against an order actually punishing someone for contempt, not against an order merely directing compliance. Since no punishment had been imposed, the impugned order was not appealable under Section 19, and the appeal was disposed of, with liberty given to the appellant to separately seek clubbing of the multiple pending cases before the single judge.

Decided 22 Sept 2026Read case
Contempt of CourtDelhi High Court

Naima Khatoon vs. Utpal Chakraborty & Anr.

The Court found that two specific cheques relied upon had never actually been presented for encashment, so no contempt arose from them. However, a receipt dated 30.11.2017 for Rs. 1,00,320 remained unclear as to whether that amount was actually collected. The Court did not impose a contempt penalty but directed that if the amount had indeed been realized by the respondents in violation of the earlier orders, it must be refunded to the petitioner with 12% annual interest within eight weeks.

Decided 21 Sept 2026Read case
Contempt of CourtDelhi High Court

Government of NCT of Delhi vs. Ram Niwas

The High Court declined to interfere, holding it saw no basis to exercise its certiorari jurisdiction over what were essentially procedural orders granting further time and recording the government's own officers' assurances of compliance: assurances given while the government was represented by two counsel, not under any unfair coercion. The Court clarified its order was not an opinion on the merits of the underlying contempt petition, which the Tribunal remains free to decide.

Decided 21 Sept 2026Read case
Contempt of CourtDelhi High Court

Teena Kapoor vs. Municipal Corporation of Delhi and Ors.

The Division Bench found that although the appellant knew of the pending litigation when she bought the flat and chose not to join those proceedings, she still faced the imminent threat of demolition without having been heard. The Court therefore directed that no demolition take place until her impleadment applications are decided by the Single Judge, permitted her to also seek impleadment in the related civil suit, and recorded her undertaking not to carry out any further construction in the meantime.

Decided 18 Sept 2026Read case