Jai Singh and Ors. v. University Grants Commission and Ors.
Background
Seven petitioners who had enrolled between 2004-2005 in an Open Distance Learning engineering degree programme at a deemed university sought a declaration that their degrees were valid without AICTE (All India Council for Technical Education) approval. Their claim ran directly against an earlier Supreme Court ruling, Orissa Lift Irrigation Corporation vs Rabi Shankar Patro, which had already held that such deemed universities needed AICTE approval and had laid out a detailed scheme requiring students in their situation to sit qualifying tests or have their degrees cancelled.
Decision Breakdown
The Court found that the petitioners' case fell squarely within the directions already issued in the Orissa Lift Irrigation judgment (specifically directions 66.4 and 66.7), and that they had, in fact, already appeared for the test that judgment required. The petitioners tried to invoke a narrow exception carved out in a different case (Jawaharlal Nehru Technological University), but the Court held that exception applied only to a State University with distinct facts, not to the petitioners' deemed university. Finding no reason to depart from its own earlier binding ruling, the Court dismissed the writ petition as devoid of merit, with no order as to costs.
Lesson Learnt
Once the Supreme Court has laid down a detailed, binding framework for a category of cases (here, distance-education engineering degrees from deemed universities), individuals within that category cannot reopen the same question in a fresh petition: they are bound by directions already issued in that earlier judgment.