Bharat Sanchar Nigam Ltd. v. Sri Deo Kumar Rai @ Deo Kumar Ray
Background
A casual labourer employed by BSNL sought "temporary status" (a step toward regularisation) under a 1989 government scheme, which required proof of having worked at least 240 days in a 12-month period. A departmental Committee examined his service records and found he had worked a maximum of only 38 days in any calendar year, making him ineligible. Despite this clear finding, the Central Administrative Tribunal and later the Gauhati High Court ruled in the worker's favour, reasoning, without recording fresh evidence, that his service from 1989 to 1998 included "artificial breaks" and should be counted cumulatively.
Decision Breakdown
The Supreme Court held that both the Tribunal and the High Court had erred by overturning the Committee's clear factual finding without any evidentiary basis, especially since an earlier High Court order had specifically directed the Tribunal to record evidence before deciding the matter afresh: a direction that was never followed. The Court clarified that the 1989 Scheme required 240 days of work within a single 12-month period, not spread cumulatively across multiple years, and that the landmark Uma Devi judgment on regularisation did not support stretching the test this way. Finding no proper basis for the lower forums' conclusion, the Court set aside their orders and allowed BSNL's appeal.
Lesson Learnt
Eligibility criteria set out in a government scheme (such as a minimum number of working days in a specific year) must be applied strictly as written: a tribunal cannot grant relief based on a sympathetic reinterpretation of the facts without recording actual evidence to support it.